Corston Windfarm (7.9 MW)

Corston Windfarm is a 7.9 MW wind farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 5 March 1996; the record was last updated on 14 April 2005.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.9 MWwind farm
refusedstatus in REPD
14 April 2005record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
5 October 1995Application submitted
5 March 1996Refused by the planning authority

Project details

Technology
wind farm
Capacity
7.9 MW
Status (REPD)
refused
Record last updated
14 April 2005
Operator or applicant
NOVERA / Renewable Energy Systems (RES)
Planning authority
Pembrokeshire
Planning application reference
not recorded
Address (REPD)
Corston Windfarm, Castlemartin, Pembrokeshire
Council area (by location)
Pembrokeshire
Time to decision
22 weeks
REPD reference
2629

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Goldborough Road, Hundletonbattery storage350approved, not built1.3
Hoplass Farmsolar farm10operational2.0
The Greenlink Converter Station - Lambeeth Battery Energy Storagebattery storage49.9approved, not built2.3
Wogaston Solar Farmsolar farm5.3operational2.3
West Orielton Farmsolar farm5application withdrawn2.6
Pembroke Power Station, Pwllcrochanbattery storage350approved, not built2.9
Chapel Hillsolar farm8operational3.5
Rhoscrowther - Turbine Wind Farmwind farm12.9refused3.6
Wear Pointwind farm8.2operational5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6561, -4.994).