Energy Projects Near You

Alleston Solar Farm (30 MW)

Alleston Solar Farm is a 30 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 March 2026, not yet built; the record was last updated on 7 May 2026. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
7 May 2026record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
16 December 2024Application submitted
10 March 2026Planning permission granted

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
7 May 2026
Operator or applicant
Stantec UK Limited
Planning authority
Welsh Government (NSIP)
Planning application reference
CAS-03072-D7X6N7
Site area
100.0 ha
Address (REPD)
Alleston Farm, Lamphey Road
Council area (by location)
Pembrokeshire
Time to decision
64 weeks
REPD reference
15560

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Golden Hillsolar farm6.2operational2.1
West Farm, Cosheston Solar Farmsolar farm9under construction3.2
Blackberry Lane Solar Farmsolar farm10approved, not built3.4
West Farm (Solar)solar farm7.7operational3.4
West Orielton Farmsolar farm5application withdrawn4.6
Chapel Hillsolar farm8operational4.8
The Greenlink Converter Station - Lambeeth Battery Energy Storagebattery storage49.9approved, not built6.5
Jordanston Solar Farmsolar farm5operational6.8
Corston Windfarmwind farm7.9refused7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6684, -4.8936).