Shoals Hook Farm (12.1 MW solar farm)

Shoals Hook Farm is a 12.1 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 3 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.1 MWsolar farm
operationalstatus in REPD
3 July 2017record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
6 May 2014Application submitted
3 October 2014Planning permission granted
1 January 2015Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
12.1 MW
Status (REPD)
operational
Record last updated
3 July 2017
Operator or applicant
John Laing Environmental Assets Group
Planning authority
Pembrokeshire
Planning application reference
14/0056/PA
Site area
26.4 ha
Address (REPD)
Land east of Shoals Hook Farm, Shoals Hook Lane, Haverfordwest, SA61 2XN
Council area (by location)
Pembrokeshire
Time to decision
21 weeks
REPD reference
2180

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crundale / Fenton Home Farm (extension)solar farm5.9operational1.5
Fenton Home Farmsolar farm31.3operational1.7
Rudbaxton Solar Parksolar farm10.8operational4.1
Cuckoo Grove Farmsolar farm6.1operational4.5
North Tenementsolar farm5operational5.2
Popehill Farmsolar farm5operational5.4
White House Farmsolar farm30application submitted5.7
Tiers Cross Solar Farmsolar farm24operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8135, -4.9417).