White House Farm (30 MW solar farm)
White House Farm is a 30 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 30 December 2025, no decision recorded; the record was last updated on 19 January 2026. It is decided by the Welsh Government as a development of national significance.
Planning timeline
| Date | Stage |
|---|---|
| 30 December 2025 | Application submitted |
Project details
- Technology
- solar farm
- Capacity
- 30 MW
- Status (REPD)
- application submitted
- Record last updated
- 19 January 2026
- Operator or applicant
- Qair UK
- Planning authority
- Welsh Government (NSIP)
- Planning application reference
- CAS-03107-C5X9W1
- Site area
- 56.6 ha
- Address (REPD)
- White House Farm, Freystrop, Haverfordwest
- Council area (by location)
- Pembrokeshire
- REPD reference
- 15561
The scheme also includes 12 MW of battery storage, recorded separately in REPD (application submitted).
Who decides
It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Popehill Farm | solar farm | 5 | operational | 1.8 |
| North Tenement | solar farm | 5 | operational | 2.1 |
| Tiers Cross Solar Farm | solar farm | 24 | operational | 5.4 |
| Shoals Hook Farm | solar farm | 12.1 | operational | 5.7 |
| Cuckoo Grove Farm | solar farm | 6.1 | operational | 5.8 |
| Dragon Energy Park Wind Farm | wind farm | 14.4 | under construction | 6.0 |
| Fenton Home Farm | solar farm | 31.3 | operational | 6.9 |
| Crundale / Fenton Home Farm (extension) | solar farm | 5.9 | operational | 7.1 |
| Wear Point | wind farm | 8.2 | operational | 7.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7642, -4.9658).