Energy Projects Near You

Solar, wind and battery projects near Haverfordwest (SA61)

22 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA61 (Pembrokeshire): 4 are waiting for a planning decision, 5 approved but not yet running, 13 operational. The largest live scheme is White House Farm (30 MW solar farm, application submitted on 30 December 2025, no decision recorded), 4.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22projects within 10 km
4awaiting a decision
5approved, not running
13operational

Projects within 10 km of SA61

Projects of 1 MW and more (14)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cuckoo Grove Farmsolar farmsolar farm6.1operationalupdated Sep 2018Nov 2012granted Apr 2013Sep 2018Pembrokeshire2.5
Shoals Hook Farmsolar farmsolar farm12.1operationalupdated Jul 2017May 2014granted Oct 2014Jul 2017Pembrokeshire2.7
North Tenementsolar farmsolar farm5operationalupdated Oct 2017Jul 2015granted May 2016Oct 2017Pembrokeshire2.7
Popehill Farmsolar farmsolar farm5operationalupdated Aug 2017Oct 2015granted May 2016Aug 2017Pembrokeshire3.1
Lawrence Landfillwind farmwind farm1.6operationalupdated May 2017Apr 2013granted Aug 2014May 2017Pembrokeshire3.4
White House Farmsolar farmsolar farm30application submittedupdated Jan 2026Dec 2025—Jan 2026Pembrokeshire4.0
White House Farmbattery storagebattery storage12application submittedupdated Jan 2026Dec 2025—Jan 2026Pembrokeshire4.0
Crundale / Fenton Home Farm (extension)solar farmsolar farm5.9operationalupdated Apr 2015Sep 2014granted Nov 2014Apr 2015Pembrokeshire4.1
Fenton Home Farmsolar farmsolar farm31.3operationalupdated Nov 2014Jul 2013granted Dec 2013Nov 2014Pembrokeshire4.4
Rudbaxton Solar Parksolar farmsolar farm10.8operationalupdated May 2014Feb 2012granted Jul 2012May 2014Pembrokeshire5.8
Tiers Cross Solar Farmsolar farmsolar farm24operationalupdated Feb 2015May 2013granted Oct 2013Feb 2015Pembrokeshire7.3
Oak Cottagesolar farmsolar farm4.9operationalupdated Nov 2015Jan 2014granted Jun 2014Nov 2015Pembrokeshire8.2
Castle Pill - Repoweringwind farmwind farm3.2operationalupdated Nov 2013Jun 2005granted Dec 2005Nov 2013Pembrokeshire9.3
Dragon Energy Park Wind Farmwind farmwind farm14.4under constructionupdated Feb 2026Jul 2023granted Oct 2024Feb 2026Pembrokeshire9.9
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Withybush Road, Fishguard Road - Micro Battery Storagebattery storagebattery storage0.2application submittedMay 2026——Pembrokeshire2.1
Puffin Producerooftop solarrooftop solar—operationalupdated Aug 2024——Aug 2024Pembrokeshire2.9
Withybush Road, Withybush Industrial Estate - Micro Energy Storage Systembattery storagebattery storage0.2application submittedMay 2026——Pembrokeshire3.2
Bolton Hill WTWsolar farmsolar farm0.5operationalupdated Jul 2020Jul 2018granted Oct 2018Jul 2020Pembrokeshire5.4
Steynton Road And Sheffield Drive - Micro Energy Battery Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2026Jul 2025granted May 2026Jun 2026Pembrokeshire8.8
Consort Equipment Products - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2024Mar 2024granted May 2024Jun 2024Pembrokeshire8.9
Honeyborough Industrial Estate - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Pembrokeshire9.2
Castle Terrace, Pill Roadbattery storagebattery storage0.2approved, not builtupdated Mar 2026Jul 2025granted Feb 2026Mar 2026Pembrokeshire10.0

Distance from the average position of the SA61 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm111010030
Rooftop solar100100
Wind farm3012014.4
Battery storage7340013.2

MW in pipeline: pending, approved and under-construction capacity.

How Pembrokeshire decides solar, wind and battery applications

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

All projects in Pembrokeshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.