Energy Projects Near You

Solar, wind and battery projects near Haverfordwest (SA62)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA62 (Pembrokeshire): 2 are waiting for a planning decision, 9 operational. The largest live scheme is Withybush Road, Withybush Industrial Estate - Micro Energy Storage System (0.2 MW battery storage, application submitted on 29 May 2026, no decision recorded), 7.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
2awaiting a decision
0approved, not running
9operational

Projects within 10 km of SA62

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cuckoo Grove Farmsolar farmsolar farm6.1operationalupdated Sep 2018Nov 2012granted Apr 2013Sep 2018Pembrokeshire5.2
Rudbaxton Solar Parksolar farmsolar farm10.8operationalupdated May 2014Feb 2012granted Jul 2012May 2014Pembrokeshire7.8
Lawrence Landfillwind farmwind farm1.6operationalupdated May 2017Apr 2013granted Aug 2014May 2017Pembrokeshire8.6
Clawddcam-Mathry Solar Farmsolar farmsolar farm7.5abandonedupdated Feb 2019May 2012granted Dec 2013Feb 2019Pembrokeshire8.8
North Tenementsolar farmsolar farm5operationalupdated Oct 2017Jul 2015granted May 2016Oct 2017Pembrokeshire8.8
Shoals Hook Farmsolar farmsolar farm12.1operationalupdated Jul 2017May 2014granted Oct 2014Jul 2017Pembrokeshire9.0
MELIN, Pen Y Bankwind farmwind farm1refusedupdated Dec 2013Feb 2013refused Oct 2013Dec 2013Pembrokeshire9.2
Popehill Farmsolar farmsolar farm5operationalupdated Aug 2017Oct 2015granted May 2016Aug 2017Pembrokeshire9.2
Crundale / Fenton Home Farm (extension)solar farmsolar farm5.9operationalupdated Apr 2015Sep 2014granted Nov 2014Apr 2015Pembrokeshire9.6
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Withybush Road, Withybush Industrial Estate - Micro Energy Storage Systembattery storagebattery storage0.2application submittedMay 2026——Pembrokeshire7.5
Puffin Producerooftop solarrooftop solar—operationalupdated Aug 2024——Aug 2024Pembrokeshire7.5
Withybush Road, Fishguard Road - Micro Battery Storagebattery storagebattery storage0.2application submittedMay 2026——Pembrokeshire7.6
Bolton Hill WTWsolar farmsolar farm0.5operationalupdated Jul 2020Jul 2018granted Oct 2018Jul 2020Pembrokeshire9.5

Distance from the average position of the SA62 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm800700
Rooftop solar100100
Wind farm200110
Battery storage220000.4

MW in pipeline: pending, approved and under-construction capacity.

How Pembrokeshire decides solar, wind and battery applications

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

All projects in Pembrokeshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.