Energy Projects Near You

Solar, wind and battery projects near Fishguard (SA65)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA65 (Pembrokeshire): 1 approved but not yet running, 1 operational. The largest live scheme is Trebover Farm (0.2 MW wind turbine, approved on 22 May 2025, not yet built), 0.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
0awaiting a decision
1approved, not running
1operational

Projects within 10 km of SA65

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Langton Farm Solar parksolar farmsolar farm4.4operationalupdated Dec 2015Mar 2013granted Nov 2013Dec 2015Pembrokeshire3.0
Trecoed Farmsolar farmsolar farm8.9permission expiredupdated Feb 2022Nov 2018granted Mar 2022Feb 2022Pembrokeshire5.1
Jordanston Wind Farmwind farmwind farm9.8refusedupdated Jul 2001Sep 1997refused Sep 2001Jul 2001Pembrokeshire5.2
Cilciffeth 'A' Wind Farmwind farmwind farm7.8refusedupdated Apr 2005Feb 1999refused Oct 1999Apr 2005Pembrokeshire5.9
Trenewydd Wind Farmwind farmwind farm6.3refusedupdated Apr 2005Feb 1999refused Oct 1999Apr 2005Pembrokeshire5.9
Cilciffeth 'B' Wind Farmwind farmwind farm7.8refusedupdated Apr 2005Feb 1999refused Oct 1999Apr 2005Pembrokeshire6.1
MELIN, Pen Y Bankwind farmwind farm1refusedupdated Dec 2013Feb 2013refused Oct 2013Dec 2013Pembrokeshire9.4
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Trebover Farmwind turbinewind turbine0.2approved, not builtupdated Jun 2025Nov 2024granted May 2025Jun 2025Pembrokeshire0.3
Fishguard Leisure Centre Car Park - Micro Energy Storagebattery storagebattery storage0.2refusedupdated Jan 2026Jul 2025refused Dec 2025Jan 2026Pembrokeshire1.6

Distance from the average position of the SA65 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200100
Wind farm500050
Wind turbine101000.2
Battery storage100010

MW in pipeline: pending, approved and under-construction capacity.

How Pembrokeshire decides solar, wind and battery applications

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

All projects in Pembrokeshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.