Energy Projects Near You

Jordanston Wind Farm (9.8 MW)

Jordanston Wind Farm is a 9.8 MW wind farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 1 September 2001; the record was last updated on 4 July 2001.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.8 MWwind farm
refusedstatus in REPD
4 July 2001record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
30 September 1997Application submitted
1 September 2001Refused by the planning authority

Project details

Technology
wind farm
Capacity
9.8 MW
Status (REPD)
refused
Record last updated
4 July 2001
Operator or applicant
RWE npower
Planning authority
Pembrokeshire
Planning application reference
97/520
Address (REPD)
Land at Jordanston south of Fishguard Dyfed
Council area (by location)
Pembrokeshire
Time to decision
205 weeks
REPD reference
2640

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Trecoed Farmsolar farm8.9permission expired0.7
Clawddcam-Mathry Solar Farmsolar farm7.5abandoned6.0
Trenewydd Wind Farmwind farm6.3refused8.4
Cilciffeth 'A' Wind Farmwind farm7.8refused8.4
Cilciffeth 'B' Wind Farmwind farm7.8refused8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9548, -5.0241).