Trenewydd Wind Farm (6.3 MW)

Trenewydd Wind Farm is a 6.3 MW wind farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 1 October 1999; the record was last updated on 14 April 2005.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.3 MWwind farm
refusedstatus in REPD
14 April 2005record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
1 February 1999Application submitted
1 October 1999Refused by the planning authority

Project details

Technology
wind farm
Capacity
6.3 MW
Status (REPD)
refused
Record last updated
14 April 2005
Operator or applicant
RWE npower
Planning authority
Pembrokeshire
Planning application reference
not recorded
Address (REPD)
Mynydd Trenewydd near Fishguard Dyfed
Council area (by location)
Pembrokeshire
Time to decision
35 weeks
REPD reference
2641

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cilciffeth 'A' Wind Farmwind farm7.8refused<0.1
Cilciffeth 'B' Wind Farmwind farm7.8refused0.3
Ambleston Solar Panelssolar farm6operational6.7
Trecoed Farmsolar farm8.9permission expired7.8
Jordanston Wind Farmwind farm9.8refused8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9552, -4.9018).