Energy Projects Near You

Trecoed Farm (8.9 MW solar farm)

Trecoed Farm is an 8.9 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 10 April 2023; the record was last updated on 9 February 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.9 MWsolar farm
permission expiredstatus in REPD
9 February 2022record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
26 November 2018Application submitted
18 March 2022Planning permission granted
10 April 2023Permission expired

Project details

Technology
solar farm
Capacity
8.9 MW
Status (REPD)
permission expired
Record last updated
9 February 2022
Operator or applicant
Transition Bro Gwaun
Planning authority
Pembrokeshire
Planning application reference
18/0858/PA
Address (REPD)
Trecoed Farm, Letterston, Haverfordwest
Council area (by location)
Pembrokeshire
Time to decision
173 weeks
REPD reference
7187

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Jordanston Wind Farmwind farm9.8refused0.7
Clawddcam-Mathry Solar Farmsolar farm7.5abandoned6.2
Trenewydd Wind Farmwind farm6.3refused7.8
Cilciffeth 'A' Wind Farmwind farm7.8refused7.8
Cilciffeth 'B' Wind Farmwind farm7.8refused8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9519, -5.0154).