Trecoed Farm (8.9 MW solar farm)
Trecoed Farm is an 8.9 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 10 April 2023; the record was last updated on 9 February 2022.
8.9 MWsolar farm
permission expiredstatus in REPD
9 February 2022record last updated
Pembrokeshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 26 November 2018 | Application submitted |
| 18 March 2022 | Planning permission granted |
| 10 April 2023 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 8.9 MW
- Status (REPD)
- permission expired
- Record last updated
- 9 February 2022
- Operator or applicant
- Transition Bro Gwaun
- Planning authority
- Pembrokeshire
- Planning application reference
- 18/0858/PA
- Address (REPD)
- Trecoed Farm, Letterston, Haverfordwest
- Council area (by location)
- Pembrokeshire
- Time to decision
- 173 weeks
- REPD reference
- 7187
Who decides
| Applications | Pembrokeshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 61 | 10,236 |
| Refused | 13 (21%) | 19% |
| Solar refused | 1 of 31 | 12% |
| Onshore wind refused | 11 of 16 | 45% |
| Battery storage refused | 1 of 14 | 16% |
| Median time from submission to decision | 23.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Jordanston Wind Farm | wind farm | 9.8 | refused | 0.7 |
| Clawddcam-Mathry Solar Farm | solar farm | 7.5 | abandoned | 6.2 |
| Trenewydd Wind Farm | wind farm | 6.3 | refused | 7.8 |
| Cilciffeth 'A' Wind Farm | wind farm | 7.8 | refused | 7.8 |
| Cilciffeth 'B' Wind Farm | wind farm | 7.8 | refused | 8.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9519, -5.0154).