Energy Projects Near You

Clawddcam-Mathry Solar Farm (7.5 MW)

Clawddcam-Mathry Solar Farm is a 7.5 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 19 February 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWsolar farm
abandonedstatus in REPD
19 February 2019record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
31 May 2012Application submitted
16 December 2013Planning permission granted
16 December 2018Permission expired

Project details

Technology
solar farm
Capacity
7.5 MW
Status (REPD)
abandoned
Record last updated
19 February 2019
Operator or applicant
Ms Power Projects Ltd
Planning authority
Pembrokeshire
Planning application reference
12/0162/PA
Address (REPD)
Haverfordwest
Council area (by location)
Pembrokeshire
Time to decision
81 weeks
REPD reference
1597

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Jordanston Wind Farmwind farm9.8refused6.0
Trecoed Farmsolar farm8.9permission expired6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9186, -5.0883).