Energy Projects Near You

Solar, wind and battery projects near Kilgetty (SA68)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA68 (Pembrokeshire): 2 are waiting for a planning decision, 4 approved but not yet running, 4 operational. The largest live scheme is Blackberry Lane Solar Farm (10 MW solar farm, approved on 15 May 2025, not yet built), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
2awaiting a decision
4approved, not running
4operational

Projects within 10 km of SA68

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Yerbeston Gate Farmsolar farmsolar farm6.1operationalupdated Feb 2016Sep 2013granted Dec 2013Feb 2016Pembrokeshire2.9
Jordanston Solar Farmsolar farmsolar farm5operationalupdated Jun 2013Jun 2012granted Sep 2012Jun 2013Pembrokeshire6.4
Land West of Roberts Wall Farsolar farmsolar farm2.5operationalupdated Mar 2016Feb 2015granted Jun 2015Mar 2016Pembrokeshire6.6
Bluestone National Park Resort, Canaston Wood Solar Farmsolar farmsolar farm4application submitted may be out of dateupdated Jan 2023Dec 2022—Jan 2023Pembrokeshire6.7
Newhouse Farm, Canaston Bridgewind farmwind farm3application withdrawnupdated Nov 2025Jun 2025—Nov 2025Pembrokeshire6.7
Princes Gate Spring Waterwind farmwind farm1.6operationalupdated Jan 2015Nov 2011granted Jul 2013Jan 2015Pembrokeshire7.2
Blackberry Lane Solar Farmsolar farmsolar farm10approved, not builtupdated Feb 2026Mar 2024granted May 2025Feb 2026Pembrokeshire7.9
West Farm, Cosheston Solar Farmsolar farmsolar farm9under constructionupdated Feb 2026Dec 2023granted Mar 2024Feb 2026Pembrokeshire9.9
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Heatherton World Of Activity, Heatherton Sports Park Solar Arrayssolar farmsolar farm0.2approved, not builtupdated Apr 2023Dec 2022granted Mar 2023Apr 2023Pembrokeshire4.8
Summerton Farm, Sagestonwind turbinewind turbine0.3refusedupdated Jul 2024Nov 2023refused Mar 2024Jul 2024Pembrokeshire5.4
Summerton Farm, Sagestonwind turbinewind turbine—application submittedupdated Jun 2025May 2025—Jun 2025Pembrokeshire5.4
Kiln Park Holiday Centre, Marsh Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Pembrokeshire7.5

Distance from the average position of the SA68 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7133023.2
Rooftop solar101000.2
Wind farm200100
Wind turbine210010

MW in pipeline: pending, approved and under-construction capacity.

How Pembrokeshire decides solar, wind and battery applications

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

All projects in Pembrokeshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SA68, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.