Solar, wind and battery projects near Narberth (SA67)
6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA67 (Pembrokeshire): 1 is waiting for a planning decision, 4 operational. The largest live scheme is Bluestone National Park Resort, Canaston Wood Solar Farm (4 MW solar farm, application submitted on 14 December 2022, no decision recorded; REPD status may be out of date), 4.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SA67
Projects of 1 MW and more (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Princes Gate Spring Waterwind farm | wind farm | 1.6 | operationalupdated Jan 2015 | Nov 2011 | granted Jul 2013 | Jan 2015 | Pembrokeshire | 3.6 |
| Bluestone National Park Resort, Canaston Wood Solar Farmsolar farm | solar farm | 4 | application submitted may be out of dateupdated Jan 2023 | Dec 2022 | — | Jan 2023 | Pembrokeshire | 4.4 |
| Newhouse Farm, Canaston Bridgewind farm | wind farm | 3 | application withdrawnupdated Nov 2025 | Jun 2025 | — | Nov 2025 | Pembrokeshire | 4.4 |
| Yerbeston Gate Farmsolar farm | solar farm | 6.1 | operationalupdated Feb 2016 | Sep 2013 | granted Dec 2013 | Feb 2016 | Pembrokeshire | 5.8 |
| Caeremlyn Solar Farmsolar farm | solar farm | 18 | operationalupdated Sep 2015 | May 2012 | granted Jan 2013 | Sep 2015 | Carmarthenshire | 8.5 |
| Oak Cottagesolar farm | solar farm | 4.9 | operationalupdated Nov 2015 | Jan 2014 | granted Jun 2014 | Nov 2015 | Pembrokeshire | 9.9 |
Distance from the average position of the SA67 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 4 | 1 | 0 | 3 | 0 | 4 |
| Wind farm | 2 | 0 | 0 | 1 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Pembrokeshire decides solar, wind and battery applications
| Applications | Pembrokeshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 61 | 10,236 |
| Refused | 13 (21%) | 19% |
| Solar refused | 1 of 31 | 12% |
| Onshore wind refused | 11 of 16 | 45% |
| Battery storage refused | 1 of 14 | 16% |
| Median time from submission to decision | 23.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 3 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SA67, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.