Energy Projects Near You

Solar, wind and battery projects near Narberth (SA67)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA67 (Pembrokeshire): 1 is waiting for a planning decision, 4 operational. The largest live scheme is Bluestone National Park Resort, Canaston Wood Solar Farm (4 MW solar farm, application submitted on 14 December 2022, no decision recorded; REPD status may be out of date), 4.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
1awaiting a decision
0approved, not running
4operational

Projects within 10 km of SA67

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Princes Gate Spring Waterwind farmwind farm1.6operationalupdated Jan 2015Nov 2011granted Jul 2013Jan 2015Pembrokeshire3.6
Bluestone National Park Resort, Canaston Wood Solar Farmsolar farmsolar farm4application submitted may be out of dateupdated Jan 2023Dec 2022—Jan 2023Pembrokeshire4.4
Newhouse Farm, Canaston Bridgewind farmwind farm3application withdrawnupdated Nov 2025Jun 2025—Nov 2025Pembrokeshire4.4
Yerbeston Gate Farmsolar farmsolar farm6.1operationalupdated Feb 2016Sep 2013granted Dec 2013Feb 2016Pembrokeshire5.8
Caeremlyn Solar Farmsolar farmsolar farm18operationalupdated Sep 2015May 2012granted Jan 2013Sep 2015Carmarthenshire8.5
Oak Cottagesolar farmsolar farm4.9operationalupdated Nov 2015Jan 2014granted Jun 2014Nov 2015Pembrokeshire9.9

Distance from the average position of the SA67 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm410304
Wind farm200100

MW in pipeline: pending, approved and under-construction capacity.

How Pembrokeshire decides solar, wind and battery applications

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

All projects in Pembrokeshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SA67, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.