Energy Projects Near You

Solar, wind and battery projects near Tenby (SA70)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA70 (Pembrokeshire): 1 is waiting for a planning decision, 3 approved but not yet running, 3 operational. The largest live scheme is Blackberry Lane Solar Farm (10 MW solar farm, approved on 15 May 2025, not yet built), 8.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
1awaiting a decision
3approved, not running
3operational

Projects within 10 km of SA70

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land West of Roberts Wall Farsolar farmsolar farm2.5operationalupdated Mar 2016Feb 2015granted Jun 2015Mar 2016Pembrokeshire0.3
Jordanston Solar Farmsolar farmsolar farm5operationalupdated Jun 2013Jun 2012granted Sep 2012Jun 2013Pembrokeshire3.7
Blackberry Lane Solar Farmsolar farmsolar farm10approved, not builtupdated Feb 2026Mar 2024granted May 2025Feb 2026Pembrokeshire8.1
Yerbeston Gate Farmsolar farmsolar farm6.1operationalupdated Feb 2016Sep 2013granted Dec 2013Feb 2016Pembrokeshire9.0
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kiln Park Holiday Centre, Marsh Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Pembrokeshire1.9
Heatherton World Of Activity, Heatherton Sports Park Solar Arrayssolar farmsolar farm0.2approved, not builtupdated Apr 2023Dec 2022granted Mar 2023Apr 2023Pembrokeshire2.2
Summerton Farm, Sagestonwind turbinewind turbine0.3refusedupdated Jul 2024Nov 2023refused Mar 2024Jul 2024Pembrokeshire3.8
Summerton Farm, Sagestonwind turbinewind turbine—application submittedupdated Jun 2025May 2025—Jun 2025Pembrokeshire3.8

Distance from the average position of the SA70 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5023010.2
Rooftop solar101000.2
Wind turbine210010

MW in pipeline: pending, approved and under-construction capacity.

How Pembrokeshire decides solar, wind and battery applications

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

All projects in Pembrokeshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.