Yerbeston Gate Farm (6.1 MW solar farm)

Yerbeston Gate Farm is a 6.1 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 November 2015; the record was last updated on 5 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.1 MWsolar farm
operationalstatus in REPD
5 February 2016record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
2 September 2013Application submitted
2 December 2013Planning permission granted
25 September 2015Construction started
25 November 2015Operational

Project details

Technology
solar farm
Capacity
6.1 MW
Status (REPD)
operational
Record last updated
5 February 2016
Operator or applicant
Sunsave 23 Limited/ Vogt solar
Planning authority
Pembrokeshire
Planning application reference
13/0501/PA
Site area
15.7 ha
Address (REPD)
Land north, west and south of Yerbeston Gate, Yerbeston, Kilgetty, SA68 0NS
Council area (by location)
Pembrokeshire
Time to decision
13 weeks
REPD reference
2365

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blackberry Lane Solar Farmsolar farm10approved, not built7.8
Jordanston Solar Farmsolar farm5operational8.0
West Farm, Cosheston Solar Farmsolar farm9under construction9.1
West Farm (Solar)solar farm7.7operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7473, -4.7945).