Energy Projects Near You

Caeremlyn Solar Farm (18 MW)

Caeremlyn Solar Farm is an 18 MW solar farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 29 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWsolar farm
operationalstatus in REPD
29 September 2015record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
31 May 2012Application submitted
14 January 2013Planning permission granted
12 February 2014Construction started
31 March 2014Operational

Project details

Technology
solar farm
Capacity
18 MW
Status (REPD)
operational
Record last updated
29 September 2015
Operator or applicant
Munich RE
Planning authority
Carmarthenshire
Planning application reference
W/26672
Address (REPD)
Caermelyn Solar Farm, Land nr Llanlliwe Farm, Hellan Amgoed, Whitland
Council area (by location)
Carmarthenshire
Time to decision
33 weeks
REPD reference
1719

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dyffryn Brodyn Wind Farmwind farm5.5operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8279, -4.6334).