Energy Projects Near You

Renewable energy projects in Carmarthenshire

72 solar, wind or battery projects of 150 kW or more are located in Carmarthenshire (REPD, July 2026 extract): 9 pending, 29 approved but not running, 19 operational and 7 refused. The council refused 10 of 61 decided applications (16%; UK 19%), with a median 22 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

72projects in the council area
9awaiting a decision
29approved, not running
16%of decisions refused

How Carmarthenshire decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Projects in Carmarthenshire

Projects of 1 MW and more (44)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Brechfa Forest Westwind farmwind farm57.4operationalupdated Sep 2018Nov 2011granted Mar 2013Sep 2018
Bryn Llywelynwind farmwind farm48.3refused on appealupdated May 2016Dec 2010refused Dec 2012May 2016
Tycroes Solar Farmsolar farmsolar farm40approved, not builtupdated Oct 2021Jun 2020granted Aug 2021Oct 2021
Brechfa Forest East Wind Farmwind farmwind farm36abandonedupdated Oct 2018Jan 2011granted Dec 2013Oct 2018
Brynrhyd Solar Farmsolar farmsolar farm36approved, not builtupdated Aug 2025Oct 2021granted Jun 2023Aug 2025
Pencoed Ganol Farm, Pendderi Roadsolar farmsolar farm35application submittedupdated Mar 2026Nov 2025—Mar 2026
Llangennech Solarsolar farmsolar farm29.9approved, not built may be out of dateupdated Nov 2021Mar 2020granted Jul 2021Nov 2021
Heol Aur, Dafen Industrial Estatebattery storagebattery storage25approved, not builtupdated Apr 2026May 2025granted Feb 2026Apr 2026
Blaengwenwind farmwind farm23operationalupdated Apr 2010Jul 2006granted Mar 2007Apr 2010
Bryncoch Solar Farmsolar farmsolar farm19abandonedupdated Oct 2019Jun 2015granted Sep 2015Oct 2019
Caeremlyn Solar Farmsolar farmsolar farm18operationalupdated Sep 2015May 2012granted Jan 2013Sep 2015
Brynteg Farmsolar farmsolar farm16.2operationalupdated Mar 2015Sep 2013granted Mar 2014Mar 2015
Clawdd Ddu PVsolar farmsolar farm13.5operationalupdated Aug 2014Mar 2013granted Oct 2013Aug 2014
Blaen Bowi Wind Farm (Extension)wind farmwind farm9.1refused on appealupdated Sep 2011Apr 2005refused Sep 2007Sep 2011
Cefn Betingau Farmsolar farmsolar farm9operationalupdated Apr 2014Jun 2013granted Aug 2013Apr 2014
MOD Pendine, Llanmiloebattery storagebattery storage8.8approved, not builtupdated Nov 2024Dec 2023granted Oct 2024Nov 2024
Parc Cynog Extensionwind farmwind farm8.4operationalupdated Nov 2017Feb 2006granted Jul 2007Nov 2017
Glyngwernen Farm, Uchaf Fawr Solar Farmsolar farmsolar farm8.4approved, not builtupdated Mar 2025Jul 2024granted Feb 2025Mar 2025
Blaen Bowi Solar parksolar farmsolar farm8abandonedupdated May 2018Sep 2013granted May 2014May 2018
Pen Y Cae solar farmsolar farmsolar farm6.9operationalupdated May 2017Apr 2013granted Sep 2013May 2017
Saron Road solar parksolar farmsolar farm6.7operationalupdated Aug 2015Apr 2013granted Sep 2013Aug 2015
Land South Of Bryn Cyrnau Isafsolar farmsolar farm5.9operationalupdated Feb 2018Mar 2015granted Jun 2015Feb 2018
Blaen Bowisolarsolar5.7permission expiredupdated Jul 2018Jan 2012granted Feb 2012Jul 2018
Ffos Las Racecoursesolar farmsolar farm5.5operationalupdated Jun 2013Nov 2010granted Apr 2011Jun 2013
Dyffryn Brodyn Wind Farmwind farmwind farm5.5operationalupdated Jun 2010—granted Jan 1994Jun 2010
Pentre farmsolar farmsolar farm5.5operationalupdated Jan 2015Dec 2012granted Mar 2013Jan 2015
Parc Cynogsolar farmsolar farm5operationalupdated Apr 2016Aug 2015granted Nov 2015Apr 2016
Tymaen Farm, Rhossolar farmsolar farm4.9application submittedupdated May 2026Apr 2026—May 2026
Mynydd Pencarregwind farmwind farm4.6approved, not builtupdated Feb 2026Mar 2015granted Mar 2016Feb 2026
Blaen Bowi Wind Farmwind farmwind farm3.9operationalupdated Aug 2004Jun 2000granted Jan 2001Aug 2004
Parc-Cynog Wind Farmwind farmwind farm3.6operationalupdated Oct 2011May 1998granted Feb 2000Oct 2011
Redcourt Farmsolar farmsolar farm3.3operationalupdated May 2015May 2014granted Oct 2014May 2015
New Lodge Farm Solarsolar farmsolar farm3refusedupdated Sep 2015Feb 2014refused Feb 2016Sep 2015
Morfa Ynys Farmlandssolar farmsolar farm3permission expiredupdated Oct 2019Oct 2015granted May 2016Oct 2019
Glyngwernen Farm, Uchaf Fawrbattery storagebattery storage2approved, not builtupdated Mar 2025Jul 2024granted Feb 2025Mar 2025
Nantycaws Waste Management Facility, Llanddarog Solar Farmsolar farmsolar farm2approved, not builtupdated Jan 2025Sep 2024granted Dec 2024Jan 2025
Morfa Pingett Solar Farmsolar farmsolar farm1.6refusedupdated Dec 2021Aug 2021refused Oct 2021Dec 2021
Pont Andrew Solar Farmsolar farmsolar farm1.5operationalupdated Mar 2013Nov 2010granted Apr 2011Mar 2013
Pistyllgwyn Farmsolar farmsolar farm1.5permission expiredupdated Aug 2019Aug 2015granted Dec 2015Aug 2019
Dura Park Bynea Industrial Siterooftop solarrooftop solar1.4operationalupdated Jun 2016Oct 2015granted Dec 2015Jun 2016
Rhas Fach Farmsolar farmsolar farm1.2permission expiredupdated Aug 2019Jul 2015granted Sep 2015Aug 2019
Blaenffos Wind Turbineswind farmwind farm1refused on appealupdated Aug 2018Jul 2014refused Jun 2015Aug 2018
Pembrey Road - Ground Mounted Solar Panelssolar farmsolar farm1approved, not builtupdated Jun 2026May 2023granted Nov 2025Jun 2026
Y Tyddyn Teg, Heol Y Nant Solar Farmsolar farmsolar farm1approved, not builtupdated Mar 2025Jun 2024granted Jan 2025Mar 2025
Smaller schemes under 1 MW, mostly rooftop solar (28)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
MOD Pendine, Llanmiloesolar farmsolar farm0.8application submitted may be out of dateupdated Jan 2024Dec 2023—Jan 2024
Bwlchgwnt Solar Parksolar farmsolar farm0.6approved, not builtupdated Apr 2022Mar 2022granted Jul 2022Apr 2022
Brecon Beacon Natural Water - Ground Mounted Solar Panelssolar farmsolar farm0.6approved, not builtupdated Jan 2026Nov 2024granted Dec 2025Jan 2026
Cwm Arian Community Solar Parksolar farmsolar farm0.5approved, not builtupdated May 2022Apr 2022granted Oct 2022May 2022
Morrisons Supermarket, -Solar Panelsrooftop solarrooftop solar0.4approved, not builtupdated Jan 2023Oct 2022granted Dec 2022Jan 2023
Blaenpant, Blaenwaunwind turbinewind turbine0.2application submitted may be out of dateupdated Sep 2023Sep 2023—Sep 2023
Cilcrug Farm, Transmawrwind turbinewind turbine0.2approved, not builtupdated Jan 2026Dec 2024granted Dec 2025Jan 2026
Penlan Isaf Farm, Portwaywind farmwind farm0.2refusedupdated Jun 2026Jan 2026refused May 2026Jun 2026
Sandy Road Solar Panels & Biomass Boilerrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Mar 2023granted Mar 2025Mar 2025
Sarnau Farm, Trelechwind turbinewind turbine0.2approved, not builtupdated Jan 2026Jun 2025granted Nov 2025Jan 2026
Anthony Way, Cillefwr Industrial Estatebattery storagebattery storage0.2approved, not builtupdated Dec 2024Jul 2024granted Nov 2024Dec 2024
Beechwood Industrial Estate - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Nov 2025Jun 2025granted Oct 2025Nov 2025
Dafen Inn Row And Exchange Rowbattery storagebattery storage0.2approved, not builtupdated Sep 2025Jul 2025granted Aug 2025Sep 2025
Heol Parc Mawr Workshops, Cross Hands - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Oct 2025Jul 2025granted Aug 2025Oct 2025
Nock Drayot Agricultural, Llysonnen Road - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Dec 2025Jul 2025granted Nov 2025Dec 2025
Parc Y Scarlets, Pemberton Athletics Track - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Sep 2025Aug 2025granted Sep 2025Sep 2025
Park Street -Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2026Feb 2026granted Apr 2026Jun 2026
Andrew Street - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Apr 2026—May 2026
The Beacon Enterprise Centre, Heol Aur - Micro Battery Storagebattery storagebattery storage0.2approved, not builtupdated Jul 2026Apr 2026granted Jun 2026Jul 2026
Ty Parc Yr Hun, Ffordd Y Rhyd - Micro Energy Storage Projectbattery storagebattery storage0.2application submittedApr 2026——
Lower Trostre Road - Micro Battery Storagebattery storagebattery storage0.2application submittedMay 2026——
North Avenue, Llanelli Workshops -Micro Energy Storagebattery storagebattery storage0.2application submittedMay 2026——
St Davids Park Solar Farmsolar farmsolar farm—application submitted may be out of dateupdated Jun 2021May 2021—Jun 2021
The Lord Arthur Rank Centre, Trostre Road - Installation of Solar Panelssolar farmsolar farm—no application requiredupdated Mar 2025——Mar 2025
Dyfed Powys Police Headquarters, Llangunnor Roadsolar farmsolar farm—approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025
Dyfed Powys Police Headquarters, Llangunnor Roadbattery storagebattery storage—approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025
Ty Cwm Gwendraeth, Gwalia Mynydd Mawrrooftop solarrooftop solar—approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026
Towy Retail Park, Old Llangunnor Roadrooftop solarrooftop solar—refusedupdated Jul 2026Apr 2026refused Jun 2026Jul 2026

Postcode districts in Carmarthenshire

DistrictProjects within 10 kmPendingApprovedOperational
SA14406189
SA15305135
SA1619392
SA178013
SA1816177
SA191010
SA200000
SA3112162
SA325012
SA339161
SA345113
SA3810113
SA393101
SA405011

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Carmarthenshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.