Parc Cynog Extension (8.4 MW wind farm)

Parc Cynog Extension is an 8.4 MW wind farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2009; the record was last updated on 2 November 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.4 MWwind farm
operationalstatus in REPD
2 November 2017record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
2 February 2006Application submitted
19 July 2007Planning permission granted
1 November 2009Operational

Project details

Technology
wind farm
Capacity
8.4 MW
Status (REPD)
operational
Record last updated
2 November 2017
Operator or applicant
Nuon
Planning authority
Carmarthenshire
Planning application reference
W/12246
Turbines
6
Address (REPD)
Parc Cynog, Pendine, Carms
Council area (by location)
Carmarthenshire
Time to decision
76 weeks
REPD reference
2950

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Parc Cynogsolar farm5operational<0.1
MOD Pendine, Llanmiloebattery storage8.8approved, not built1.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7592, -4.5337).