Parc Cynog Extension (8.4 MW wind farm)
Parc Cynog Extension is an 8.4 MW wind farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2009; the record was last updated on 2 November 2017.
8.4 MWwind farm
operationalstatus in REPD
2 November 2017record last updated
Carmarthenshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 2 February 2006 | Application submitted |
| 19 July 2007 | Planning permission granted |
| 1 November 2009 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 8.4 MW
- Status (REPD)
- operational
- Record last updated
- 2 November 2017
- Operator or applicant
- Nuon
- Planning authority
- Carmarthenshire
- Planning application reference
- W/12246
- Turbines
- 6
- Address (REPD)
- Parc Cynog, Pendine, Carms
- Council area (by location)
- Carmarthenshire
- Time to decision
- 76 weeks
- REPD reference
- 2950
Who decides
| Applications | Carmarthenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 61 | 10,236 |
| Refused | 10 (16%) | 19% |
| Solar refused | 5 of 34 | 12% |
| Onshore wind refused | 5 of 14 | 45% |
| Battery storage refused | 0 of 13 | 16% |
| Median time from submission to decision | 21.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Parc Cynog | solar farm | 5 | operational | <0.1 |
| MOD Pendine, Llanmiloe | battery storage | 8.8 | approved, not built | 1.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7592, -4.5337).