Energy Projects Near You

Parc Cynog (5 MW solar farm)

Parc Cynog is a 5 MW solar farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 March 2016; the record was last updated on 1 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
1 April 2016record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
10 August 2015Application submitted
10 November 2015Planning permission granted
18 January 2016Construction started
24 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
1 April 2016
Operator or applicant
Vattenfall
Planning authority
Carmarthenshire
Planning application reference
W/32580
Site area
10.7 ha
Address (REPD)
Parc Cynog, Pendine, Carms
Council area (by location)
Carmarthenshire
Time to decision
13 weeks
REPD reference
5499

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Parc Cynog Extensionwind farm8.4operational<0.1
MOD Pendine, Llanmiloebattery storage8.8approved, not built1.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7592, -4.5337).