MOD Pendine, Llanmiloe (8.8 MW battery storage)

MOD Pendine, Llanmiloe is an 8.8 MW battery storage project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 October 2024, not yet built; the record was last updated on 26 November 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.8 MWbattery storage
approved, not builtstatus in REPD
26 November 2024record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
18 December 2023Application submitted
9 October 2024Planning permission granted

Project details

Technology
battery storage (co-located with re)
Capacity
8.8 MW
Status (REPD)
approved, not built
Record last updated
26 November 2024
Operator or applicant
QinetiQ
Planning authority
Carmarthenshire
Planning application reference
PL/07023
Address (REPD)
MOD Pendine, Llanmiloe, Carmarthenshire
Council area (by location)
Carmarthenshire
Time to decision
42 weeks
Name in REPD
MOD Pendine, Llanmiloe - Solar Panels
REPD reference
15630

The scheme also includes 0.8 MW of solar farm, recorded separately in REPD (application submitted).

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Parc Cynog Extensionwind farm8.4operational1.4
Parc Cynogsolar farm5operational1.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7498, -4.5208).