Glyngwernen Farm, Uchaf Fawr Solar Farm (8.4 MW)

Glyngwernen Farm, Uchaf Fawr Solar Farm is an 8.4 MW solar farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 February 2025, not yet built; the record was last updated on 10 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.4 MWsolar farm
approved, not builtstatus in REPD
10 March 2025record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
17 July 2024Application submitted
17 February 2025Planning permission granted
17 February 2030Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
8.4 MW
Status (REPD)
approved, not built
Record last updated
10 March 2025
Operator or applicant
Bartypower Limited
Planning authority
Carmarthenshire
Planning application reference
PL/08017
Site area
12.8 ha
Address (REPD)
N/O Glyngwernen Farm, Uchaf Fawr, Felinfoel, Llanelli, Dyfed
Council area (by location)
Carmarthenshire
Time to decision
31 weeks
Name in REPD
Glyngwernen Farm, Uchaf Fawr - Solar Farm
REPD reference
16838

Recorded together with Glyngwernen Farm, Uchaf Fawr (2 MW battery storage, approved, not built).

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Heol Aur, Dafen Industrial Estatebattery storage25approved, not built0.7
Llangennech Solarsolar farm29.9approved, not built2.3
Pencoed Ganol Farm, Pendderi Roadsolar farm35application submitted2.7
Brynteg Farmsolar farm16.2operational4.2
Coed Bach Park, Gwynfryn Roadrooftop solar15application submitted5.8
Pentre farmsolar farm5.5operational6.2
Castell Ddu Solar Farmsolar farm5permission expired6.3
Gwenlais Solar Farmsolar farm16.3approved, not built7.2
Brynrhyd Solar Farmsolar farm36approved, not built7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7028, -4.119).