Llangennech Solar (29.9 MW)

Llangennech Solar is a 29.9 MW solar farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 July 2021, not yet built; the record was last updated on 30 November 2021. It is decided by the Welsh Government as a development of national significance. REPD also records that the planning permission expired on 23 July 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
30 November 2021record last updated
Carmarthenshirecouncil area

REPD also records that the planning permission expired on 23 July 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
19 March 2020Application submitted
23 July 2021Planning permission granted
23 July 2026Permission expired

Project details

Technology
solar farm
Capacity
29.9 MW
Status (REPD)
approved, not built
Record last updated
30 November 2021
Operator or applicant
Voltalia UK
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3213164
Site area
96.3 ha
Address (REPD)
Land At Penderi, Blaenhiraeth, Llangennech, Llanelli, Dyfed
Council area (by location)
Carmarthenshire
Time to decision
70 weeks
REPD reference
6795

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Glyngwernen Farm, Uchaf Fawr Solar Farmsolar farm8.4approved, not built2.3
Heol Aur, Dafen Industrial Estatebattery storage25approved, not built2.9
Pentre farmsolar farm5.5operational4.1
Pencoed Ganol Farm, Pendderi Roadsolar farm35application submitted4.6
Brynteg Farmsolar farm16.2operational4.7
Coed Bach Park, Gwynfryn Roadrooftop solar15application submitted5.4
Brynrhyd Solar Farmsolar farm36approved, not built5.8
Castell Ddu Solar Farmsolar farm5permission expired6.4
Tycroes Solar Farmsolar farm40approved, not built7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7225, -4.1109).