Energy Projects Near You

Solar, wind and battery projects near Swansea (SA4)

51 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA4 (Swansea): 9 are waiting for a planning decision, 24 approved but not yet running, 8 operational. The largest live scheme is Lletty Scilp Farm, Swansea North (400 MW battery storage, approved on 19 May 2026, not yet built), 6.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

51projects within 10 km
9awaiting a decision
24approved, not running
8operational

Projects within 10 km of SA4

Projects of 1 MW and more (29)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Pencefnarda Uchaf Farmsolar farmsolar farm3.6refused on appealupdated Oct 2015Jun 2014refused Feb 2015Oct 2015Swansea1.0
Castell Ddu Solar Farmsolar farmsolar farm5permission expiredupdated Mar 2020Sep 2015granted Jan 2016Mar 2020Swansea2.8
Dura Park Bynea Industrial Siterooftop solarrooftop solar1.4operationalupdated Jun 2016Oct 2015granted Dec 2015Jun 2016Carmarthenshire2.9
Gwenlais Solar Farmsolar farmsolar farm16.3approved, not builtupdated May 2026Mar 2024granted Jun 2025May 2026Swansea3.1
Parc Solar Caenewyddbattery storagebattery storage46under constructionupdated Jun 2026Jun 2024granted Dec 2024Jun 2026Swansea3.3
Parc Solar Caenewyddsolar farmsolar farm42under constructionupdated Jun 2026Jun 2024granted Dec 2024Jun 2026Swansea3.3
Pencoed Ganol Farm, Pendderi Roadsolar farmsolar farm35application submittedupdated Mar 2026Nov 2025—Mar 2026Carmarthenshire3.8
Coed Bach Park, Gwynfryn Roadrooftop solarrooftop solar15application submittedupdated Sep 2025Aug 2025—Sep 2025Swansea4.3
Timet UKwind farmwind farm2refusedupdated Jul 2005Sep 2003refused Aug 2004Jul 2005Swansea4.4
Cockett Valleysolar farmsolar farm4operationalupdated Oct 2017Dec 2014granted Aug 2015Oct 2017Swansea4.7
Gelliwern Isaf Farmsolar farmsolar farm6operationalupdated Jun 2015May 2014granted Nov 2014Jun 2015Swansea4.8
Killan Farm Solar Array Extenssolar farmsolar farm1operationalupdated Jan 2018Jul 2015granted Dec 2015Jan 2018Swansea5.2
Bryntywod, Llangyfelachbattery storagebattery storage200approved, not builtupdated Feb 2025Sep 2024granted Feb 2025Feb 2025Swansea5.8
Glyngwernen Farm, Uchaf Fawr Solar Farmsolar farmsolar farm8.4approved, not builtupdated Mar 2025Jul 2024granted Feb 2025Mar 2025Carmarthenshire5.9
Glyngwernen Farm, Uchaf Fawrbattery storagebattery storage2approved, not builtupdated Mar 2025Jul 2024granted Feb 2025Mar 2025Carmarthenshire5.9
Brynwhilach Solar Farm, Morristonbattery storagebattery storage1approved, not builtupdated Apr 2023Jan 2023granted Mar 2023Apr 2023Swansea6.0
Heol Aur, Dafen Industrial Estatebattery storagebattery storage25approved, not builtupdated Apr 2026May 2025granted Feb 2026Apr 2026Carmarthenshire6.1
Solar Farm at The E/O Pontlliwsolar farmsolar farm40application submittedupdated Oct 2025Apr 2025—Oct 2025Swansea6.1
Morfa Ynys Farmlandssolar farmsolar farm3permission expiredupdated Oct 2019Oct 2015granted May 2016Oct 2019Carmarthenshire6.1
Brynwhilach Solar Parksolar farmsolar farm4operationalupdated Mar 2022Jul 2014granted Nov 2014Mar 2022Swansea6.4
Lletty Scilp Farm, Swansea Northbattery storagebattery storage400approved, not builtupdated Jun 2026Mar 2025granted May 2026Jun 2026Swansea6.6
Land at Lltty Morphil Farmsolar farmsolar farm5abandonedupdated Mar 2020Jul 2015granted May 2016Mar 2020Swansea6.6
Llangennech Solarsolar farmsolar farm29.9approved, not built may be out of dateupdated Nov 2021Mar 2020granted Jul 2021Nov 2021Carmarthenshire7.0
Abergelli Farm, Felindrebattery storagebattery storage250application submittedupdated Aug 2025Jul 2025—Aug 2025Swansea7.1
Abergelli Glas Solar Farmsolar farmsolar farm7.7operationalupdated Sep 2018Feb 2013granted May 2013Sep 2018Swansea7.6
Rhyd-y-Pandy Solar Farmsolar farmsolar farm6operationalupdated May 2015Nov 2013granted Feb 2014May 2015Swansea7.9
Webbsfieldsolar farmsolar farm1refused on appealupdated May 2015Jun 2014refused Sep 2014May 2015Swansea8.7
Brynrhyd Solar Farmsolar farmsolar farm36approved, not builtupdated Aug 2025Oct 2021granted Jun 2023Aug 2025Carmarthenshire9.0
Brynteg Farmsolar farmsolar farm16.2operationalupdated Mar 2015Sep 2013granted Mar 2014Mar 2015Carmarthenshire10.0
Smaller schemes under 1 MW, mostly rooftop solar (22)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Heol Y Mynydd Road - Micro Energy Storagebattery storagebattery storage0.2refusedupdated Jun 2026Feb 2026refused Apr 2026Jun 2026Swansea0.9
Garngoch Industrial Estate, Penllergaer - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated May 2025May 2025granted Jun 2025May 2025Swansea2.4
Gwenlais Solar Farmbattery storagebattery storage—approved, not builtupdated May 2026Nov 2022granted Jun 2025May 2026Swansea3.1
Tesco Superstore, Tidal Reachrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Dec 2025granted Jan 2026Jan 2026Swansea4.5
The Beacon Enterprise Centre, Heol Aur - Micro Battery Storagebattery storagebattery storage0.2approved, not builtupdated Jul 2026Apr 2026granted Jun 2026Jul 2026Carmarthenshire5.5
Parc Y Scarlets, Pemberton Athletics Track - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Sep 2025Aug 2025granted Sep 2025Sep 2025Carmarthenshire5.7
Dafen Inn Row And Exchange Rowbattery storagebattery storage0.2approved, not builtupdated Sep 2025Jul 2025granted Aug 2025Sep 2025Carmarthenshire5.8
Morrisons Supermarket, -Solar Panelsrooftop solarrooftop solar0.4approved, not builtupdated Jan 2023Oct 2022granted Dec 2022Jan 2023Carmarthenshire5.9
North Avenue, Llanelli Workshops -Micro Energy Storagebattery storagebattery storage0.2application submittedMay 2026——Carmarthenshire6.3
Lower Trostre Road - Micro Battery Storagebattery storagebattery storage0.2application submittedMay 2026——Carmarthenshire6.5
The Lord Arthur Rank Centre, Trostre Road - Installation of Solar Panelssolar farmsolar farm—no application requiredupdated Mar 2025——Mar 2025Carmarthenshire6.6
Swansea Greener Grid Parkbattery storagebattery storage—under constructionupdated Apr 2025Jan 2021granted Aug 2021Apr 2025Swansea7.1
Hazel Court, Sketty Parkrooftop solarrooftop solar—refusedupdated May 2023Apr 2023refused May 2023May 2023Swansea7.2
Andrew Street - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Apr 2026—May 2026Carmarthenshire7.5
Morfa Stadium, Normandy Roadbattery storagebattery storage0.2approved, not builtupdated Jun 2026Feb 2026granted Apr 2026Jun 2026Swansea8.7
Brunel Way, Pentrechwythrooftop solarrooftop solar0.7approved, not builtupdated Feb 2022Feb 2022granted Mar 2022Feb 2022Swansea9.0
Kemys Way, Swansea Enterprise Parkbattery storagebattery storage0.2application submittedupdated May 2025May 2025—May 2025Swansea9.1
Kemys Way - Micro Energy Storage Facilitybattery storagebattery storage0.2application submittedupdated May 2025May 2025—May 2025Swansea9.4
Ferryboat Close, Swansea Enterprise Park - Micro Energy Storage Unitbattery storagebattery storage0.2approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Swansea9.4
Swansea Enterprise Park, Clarion Close Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Jul 2025Apr 2025refused Jun 2025Jul 2025Swansea9.4
Sandy Road Solar Panels & Biomass Boilerrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Mar 2023granted Mar 2025Mar 2025Carmarthenshire9.4
Eurofoods Buildingrooftop solarrooftop solar0.6approved, not built may be out of dateupdated Apr 2019Feb 2019granted Apr 2019Apr 2019Swansea9.7

Distance from the average position of the SA4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm202572208
Rooftop solar8151117.2
Wind farm100010
Battery storage2261402926

MW in pipeline: pending, approved and under-construction capacity.

How Swansea decides solar, wind and battery applications

ApplicationsSwanseaUK
Decided applications (solar, wind, battery)3510,236
Refused9 (26%)19%
Solar refused5 of 2012%
Onshore wind refused2 of 345%
Battery storage refused2 of 1216%
Median time from submission to decision18.1 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

All projects in Swansea

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SA4, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.