Solar, wind and battery projects near Llanelli (SA14)
40 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA14 (Carmarthenshire): 6 are waiting for a planning decision, 18 approved but not yet running, 9 operational. The largest live scheme is Tycroes Solar Farm (40 MW solar farm, approved on 12 August 2021, not yet built), 5.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SA14
Projects of 1 MW and more (24)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Llangennech Solarsolar farm | solar farm | 29.9 | approved, not built may be out of dateupdated Nov 2021 | Mar 2020 | granted Jul 2021 | Nov 2021 | Carmarthenshire | 1.5 |
| Y Tyddyn Teg, Heol Y Nant Solar Farmsolar farm | solar farm | 1 | approved, not builtupdated Mar 2025 | Jun 2024 | granted Jan 2025 | Mar 2025 | Carmarthenshire | 2.6 |
| Pentre farmsolar farm | solar farm | 5.5 | operationalupdated Jan 2015 | Dec 2012 | granted Mar 2013 | Jan 2015 | Carmarthenshire | 2.8 |
| Glyngwernen Farm, Uchaf Fawr Solar Farmsolar farm | solar farm | 8.4 | approved, not builtupdated Mar 2025 | Jul 2024 | granted Feb 2025 | Mar 2025 | Carmarthenshire | 3.7 |
| Glyngwernen Farm, Uchaf Fawrbattery storage | battery storage | 2 | approved, not builtupdated Mar 2025 | Jul 2024 | granted Feb 2025 | Mar 2025 | Carmarthenshire | 3.7 |
| Heol Aur, Dafen Industrial Estatebattery storage | battery storage | 25 | approved, not builtupdated Apr 2026 | May 2025 | granted Feb 2026 | Apr 2026 | Carmarthenshire | 4.4 |
| New Lodge Farm Solarsolar farm | solar farm | 3 | refusedupdated Sep 2015 | Feb 2014 | refused Feb 2016 | Sep 2015 | Carmarthenshire | 4.4 |
| Brynrhyd Solar Farmsolar farm | solar farm | 36 | approved, not builtupdated Aug 2025 | Oct 2021 | granted Jun 2023 | Aug 2025 | Carmarthenshire | 4.8 |
| Pont Andrew Solar Farmsolar farm | solar farm | 1.5 | operationalupdated Mar 2013 | Nov 2010 | granted Apr 2011 | Mar 2013 | Carmarthenshire | 4.9 |
| Brynteg Farmsolar farm | solar farm | 16.2 | operationalupdated Mar 2015 | Sep 2013 | granted Mar 2014 | Mar 2015 | Carmarthenshire | 5.6 |
| Coed Bach Park, Gwynfryn Roadrooftop solar | rooftop solar | 15 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | Swansea | 5.6 |
| Tycroes Solar Farmsolar farm | solar farm | 40 | approved, not builtupdated Oct 2021 | Jun 2020 | granted Aug 2021 | Oct 2021 | Carmarthenshire | 5.7 |
| Pencoed Ganol Farm, Pendderi Roadsolar farm | solar farm | 35 | application submittedupdated Mar 2026 | Nov 2025 | — | Mar 2026 | Carmarthenshire | 6.0 |
| Clawdd Ddu PVsolar farm | solar farm | 13.5 | operationalupdated Aug 2014 | Mar 2013 | granted Oct 2013 | Aug 2014 | Carmarthenshire | 6.1 |
| Castell Ddu Solar Farmsolar farm | solar farm | 5 | permission expiredupdated Mar 2020 | Sep 2015 | granted Jan 2016 | Mar 2020 | Swansea | 7.0 |
| Pencefnarda Uchaf Farmsolar farm | solar farm | 3.6 | refused on appealupdated Oct 2015 | Jun 2014 | refused Feb 2015 | Oct 2015 | Swansea | 7.0 |
| Morfa Ynys Farmlandssolar farm | solar farm | 3 | permission expiredupdated Oct 2019 | Oct 2015 | granted May 2016 | Oct 2019 | Carmarthenshire | 7.6 |
| Dura Park Bynea Industrial Siterooftop solar | rooftop solar | 1.4 | operationalupdated Jun 2016 | Oct 2015 | granted Dec 2015 | Jun 2016 | Carmarthenshire | 7.6 |
| Pen Y Cae solar farmsolar farm | solar farm | 6.9 | operationalupdated May 2017 | Apr 2013 | granted Sep 2013 | May 2017 | Carmarthenshire | 7.8 |
| Gwenlais Solar Farmsolar farm | solar farm | 16.3 | approved, not builtupdated May 2026 | Mar 2024 | granted Jun 2025 | May 2026 | Swansea | 7.9 |
| Gelliwern Isaf Farmsolar farm | solar farm | 6 | operationalupdated Jun 2015 | May 2014 | granted Nov 2014 | Jun 2015 | Swansea | 8.8 |
| Rhas Fach Farmsolar farm | solar farm | 1.2 | permission expiredupdated Aug 2019 | Jul 2015 | granted Sep 2015 | Aug 2019 | Carmarthenshire | 8.8 |
| Saron Road solar parksolar farm | solar farm | 6.7 | operationalupdated Aug 2015 | Apr 2013 | granted Sep 2013 | Aug 2015 | Carmarthenshire | 9.0 |
| Ffos Las Racecoursesolar farm | solar farm | 5.5 | operationalupdated Jun 2013 | Nov 2010 | granted Apr 2011 | Jun 2013 | Carmarthenshire | 9.2 |
Smaller schemes under 1 MW, mostly rooftop solar (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Ty Cwm Gwendraeth, Gwalia Mynydd Mawrrooftop solar | rooftop solar | — | approved, not builtupdated Apr 2026 | Jan 2026 | granted Feb 2026 | Apr 2026 | Carmarthenshire | 4.0 |
| The Beacon Enterprise Centre, Heol Aur - Micro Battery Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2026 | Apr 2026 | granted Jun 2026 | Jul 2026 | Carmarthenshire | 4.4 |
| Tesco Superstore, Tidal Reachrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Dec 2025 | granted Jan 2026 | Jan 2026 | Swansea | 5.0 |
| Dafen Inn Row And Exchange Rowbattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Aug 2025 | Sep 2025 | Carmarthenshire | 5.2 |
| Morrisons Supermarket, -Solar Panelsrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2023 | Oct 2022 | granted Dec 2022 | Jan 2023 | Carmarthenshire | 6.4 |
| Parc Y Scarlets, Pemberton Athletics Track - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2025 | Aug 2025 | granted Sep 2025 | Sep 2025 | Carmarthenshire | 6.4 |
| Andrew Street - Micro Energy Storagebattery storage | battery storage | 0.2 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | Carmarthenshire | 6.6 |
| Heol Parc Mawr Workshops, Cross Hands - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Oct 2025 | Jul 2025 | granted Aug 2025 | Oct 2025 | Carmarthenshire | 6.9 |
| North Avenue, Llanelli Workshops -Micro Energy Storagebattery storage | battery storage | 0.2 | application submitted | May 2026 | — | — | Carmarthenshire | 7.3 |
| The Lord Arthur Rank Centre, Trostre Road - Installation of Solar Panelssolar farm | solar farm | — | no application requiredupdated Mar 2025 | — | — | Mar 2025 | Carmarthenshire | 7.3 |
| Lower Trostre Road - Micro Battery Storagebattery storage | battery storage | 0.2 | application submitted | May 2026 | — | — | Carmarthenshire | 7.6 |
| Sandy Road Solar Panels & Biomass Boilerrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Mar 2023 | granted Mar 2025 | Mar 2025 | Carmarthenshire | 7.8 |
| Gwenlais Solar Farmbattery storage | battery storage | — | approved, not builtupdated May 2026 | Nov 2022 | granted Jun 2025 | May 2026 | Swansea | 7.9 |
| Heol Y Mynydd Road - Micro Energy Storagebattery storage | battery storage | 0.2 | refusedupdated Jun 2026 | Feb 2026 | refused Apr 2026 | Jun 2026 | Swansea | 8.8 |
| Ty Parc Yr Hun, Ffordd Y Rhyd - Micro Energy Storage Projectbattery storage | battery storage | 0.2 | application submitted | Apr 2026 | — | — | Carmarthenshire | 9.7 |
| Garngoch Industrial Estate, Penllergaer - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | May 2025 | granted Jun 2025 | May 2025 | Swansea | 10.0 |
Distance from the average position of the SA14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 21 | 1 | 6 | 8 | 2 | 167 |
| Rooftop solar | 6 | 1 | 4 | 1 | 0 | 15.9 |
| Battery storage | 13 | 4 | 8 | 0 | 1 | 28.8 |
MW in pipeline: pending, approved and under-construction capacity.
How Carmarthenshire decides solar, wind and battery applications
| Applications | Carmarthenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 61 | 10,236 |
| Refused | 10 (16%) | 19% |
| Solar refused | 5 of 34 | 12% |
| Onshore wind refused | 5 of 14 | 45% |
| Battery storage refused | 0 of 13 | 16% |
| Median time from submission to decision | 21.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
All projects in Carmarthenshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SA14, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.