Energy Projects Near You

Solar, wind and battery projects near Llanelli (SA14)

40 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA14 (Carmarthenshire): 6 are waiting for a planning decision, 18 approved but not yet running, 9 operational. The largest live scheme is Tycroes Solar Farm (40 MW solar farm, approved on 12 August 2021, not yet built), 5.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40projects within 10 km
6awaiting a decision
18approved, not running
9operational

Projects within 10 km of SA14

Projects of 1 MW and more (24)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Llangennech Solarsolar farmsolar farm29.9approved, not built may be out of dateupdated Nov 2021Mar 2020granted Jul 2021Nov 2021Carmarthenshire1.5
Y Tyddyn Teg, Heol Y Nant Solar Farmsolar farmsolar farm1approved, not builtupdated Mar 2025Jun 2024granted Jan 2025Mar 2025Carmarthenshire2.6
Pentre farmsolar farmsolar farm5.5operationalupdated Jan 2015Dec 2012granted Mar 2013Jan 2015Carmarthenshire2.8
Glyngwernen Farm, Uchaf Fawr Solar Farmsolar farmsolar farm8.4approved, not builtupdated Mar 2025Jul 2024granted Feb 2025Mar 2025Carmarthenshire3.7
Glyngwernen Farm, Uchaf Fawrbattery storagebattery storage2approved, not builtupdated Mar 2025Jul 2024granted Feb 2025Mar 2025Carmarthenshire3.7
Heol Aur, Dafen Industrial Estatebattery storagebattery storage25approved, not builtupdated Apr 2026May 2025granted Feb 2026Apr 2026Carmarthenshire4.4
New Lodge Farm Solarsolar farmsolar farm3refusedupdated Sep 2015Feb 2014refused Feb 2016Sep 2015Carmarthenshire4.4
Brynrhyd Solar Farmsolar farmsolar farm36approved, not builtupdated Aug 2025Oct 2021granted Jun 2023Aug 2025Carmarthenshire4.8
Pont Andrew Solar Farmsolar farmsolar farm1.5operationalupdated Mar 2013Nov 2010granted Apr 2011Mar 2013Carmarthenshire4.9
Brynteg Farmsolar farmsolar farm16.2operationalupdated Mar 2015Sep 2013granted Mar 2014Mar 2015Carmarthenshire5.6
Coed Bach Park, Gwynfryn Roadrooftop solarrooftop solar15application submittedupdated Sep 2025Aug 2025—Sep 2025Swansea5.6
Tycroes Solar Farmsolar farmsolar farm40approved, not builtupdated Oct 2021Jun 2020granted Aug 2021Oct 2021Carmarthenshire5.7
Pencoed Ganol Farm, Pendderi Roadsolar farmsolar farm35application submittedupdated Mar 2026Nov 2025—Mar 2026Carmarthenshire6.0
Clawdd Ddu PVsolar farmsolar farm13.5operationalupdated Aug 2014Mar 2013granted Oct 2013Aug 2014Carmarthenshire6.1
Castell Ddu Solar Farmsolar farmsolar farm5permission expiredupdated Mar 2020Sep 2015granted Jan 2016Mar 2020Swansea7.0
Pencefnarda Uchaf Farmsolar farmsolar farm3.6refused on appealupdated Oct 2015Jun 2014refused Feb 2015Oct 2015Swansea7.0
Morfa Ynys Farmlandssolar farmsolar farm3permission expiredupdated Oct 2019Oct 2015granted May 2016Oct 2019Carmarthenshire7.6
Dura Park Bynea Industrial Siterooftop solarrooftop solar1.4operationalupdated Jun 2016Oct 2015granted Dec 2015Jun 2016Carmarthenshire7.6
Pen Y Cae solar farmsolar farmsolar farm6.9operationalupdated May 2017Apr 2013granted Sep 2013May 2017Carmarthenshire7.8
Gwenlais Solar Farmsolar farmsolar farm16.3approved, not builtupdated May 2026Mar 2024granted Jun 2025May 2026Swansea7.9
Gelliwern Isaf Farmsolar farmsolar farm6operationalupdated Jun 2015May 2014granted Nov 2014Jun 2015Swansea8.8
Rhas Fach Farmsolar farmsolar farm1.2permission expiredupdated Aug 2019Jul 2015granted Sep 2015Aug 2019Carmarthenshire8.8
Saron Road solar parksolar farmsolar farm6.7operationalupdated Aug 2015Apr 2013granted Sep 2013Aug 2015Carmarthenshire9.0
Ffos Las Racecoursesolar farmsolar farm5.5operationalupdated Jun 2013Nov 2010granted Apr 2011Jun 2013Carmarthenshire9.2
Smaller schemes under 1 MW, mostly rooftop solar (16)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ty Cwm Gwendraeth, Gwalia Mynydd Mawrrooftop solarrooftop solar—approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Carmarthenshire4.0
The Beacon Enterprise Centre, Heol Aur - Micro Battery Storagebattery storagebattery storage0.2approved, not builtupdated Jul 2026Apr 2026granted Jun 2026Jul 2026Carmarthenshire4.4
Tesco Superstore, Tidal Reachrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Dec 2025granted Jan 2026Jan 2026Swansea5.0
Dafen Inn Row And Exchange Rowbattery storagebattery storage0.2approved, not builtupdated Sep 2025Jul 2025granted Aug 2025Sep 2025Carmarthenshire5.2
Morrisons Supermarket, -Solar Panelsrooftop solarrooftop solar0.4approved, not builtupdated Jan 2023Oct 2022granted Dec 2022Jan 2023Carmarthenshire6.4
Parc Y Scarlets, Pemberton Athletics Track - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Sep 2025Aug 2025granted Sep 2025Sep 2025Carmarthenshire6.4
Andrew Street - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Apr 2026—May 2026Carmarthenshire6.6
Heol Parc Mawr Workshops, Cross Hands - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Oct 2025Jul 2025granted Aug 2025Oct 2025Carmarthenshire6.9
North Avenue, Llanelli Workshops -Micro Energy Storagebattery storagebattery storage0.2application submittedMay 2026——Carmarthenshire7.3
The Lord Arthur Rank Centre, Trostre Road - Installation of Solar Panelssolar farmsolar farm—no application requiredupdated Mar 2025——Mar 2025Carmarthenshire7.3
Lower Trostre Road - Micro Battery Storagebattery storagebattery storage0.2application submittedMay 2026——Carmarthenshire7.6
Sandy Road Solar Panels & Biomass Boilerrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Mar 2023granted Mar 2025Mar 2025Carmarthenshire7.8
Gwenlais Solar Farmbattery storagebattery storage—approved, not builtupdated May 2026Nov 2022granted Jun 2025May 2026Swansea7.9
Heol Y Mynydd Road - Micro Energy Storagebattery storagebattery storage0.2refusedupdated Jun 2026Feb 2026refused Apr 2026Jun 2026Swansea8.8
Ty Parc Yr Hun, Ffordd Y Rhyd - Micro Energy Storage Projectbattery storagebattery storage0.2application submittedApr 2026——Carmarthenshire9.7
Garngoch Industrial Estate, Penllergaer - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated May 2025May 2025granted Jun 2025May 2025Swansea10.0

Distance from the average position of the SA14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm211682167
Rooftop solar6141015.9
Battery storage13480128.8

MW in pipeline: pending, approved and under-construction capacity.

How Carmarthenshire decides solar, wind and battery applications

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in Carmarthenshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SA14, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.