Energy Projects Near You

Clawdd Ddu PV (13.5 MW)

Clawdd Ddu PV is a 13.5 MW solar farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 March 2014; the record was last updated on 26 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.5 MWsolar farm
operationalstatus in REPD
26 August 2014record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
27 March 2013Application submitted
7 October 2013Planning permission granted
26 March 2014Operational

Project details

Technology
solar farm
Capacity
13.5 MW
Status (REPD)
operational
Record last updated
26 August 2014
Operator or applicant
Elgin Energy EsCo
Planning authority
Carmarthenshire
Planning application reference
S/27987
Address (REPD)
Potardulas Road, Tycroes, Swansea
Council area (by location)
Carmarthenshire
Time to decision
28 weeks
REPD reference
1951

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tycroes Solar Farmsolar farm40approved, not built0.9
Brynrhyd Solar Farmsolar farm36approved, not built1.9
Pen Y Cae solar farmsolar farm6.9operational1.9
Saron Road solar parksolar farm6.7operational3.0
Pentre farmsolar farm5.5operational6.0
Coed Bach Park, Gwynfryn Roadrooftop solar15application submitted6.7
Cefn Betingau Farmsolar farm9operational7.0
Mynydd Y Gwair Wind Farmwind farm32.8operational7.3
Llangennech Solarsolar farm29.9approved, not built7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7708, -4.038).