Pentre farm (5.5 MW solar farm)

Pentre farm is a 5.5 MW solar farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 September 2014; the record was last updated on 19 January 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.5 MWsolar farm
operationalstatus in REPD
19 January 2015record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
18 December 2012Application submitted
11 March 2013Planning permission granted
25 September 2014Operational

Project details

Technology
solar farm
Capacity
5.5 MW
Status (REPD)
operational
Record last updated
19 January 2015
Operator or applicant
Kinetica Solar
Planning authority
Carmarthenshire
Planning application reference
S/27526
Address (REPD)
Pentre Farm, Llannon, Llanelli
Council area (by location)
Carmarthenshire
Time to decision
12 weeks
REPD reference
4938

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Llangennech Solarsolar farm29.9approved, not built4.1
Tycroes Solar Farmsolar farm40approved, not built5.3
Brynrhyd Solar Farmsolar farm36approved, not built5.5
Clawdd Ddu PVsolar farm13.5operational6.0
Glyngwernen Farm, Uchaf Fawr Solar Farmsolar farm8.4approved, not built6.2
Brynteg Farmsolar farm16.2operational6.4
Heol Aur, Dafen Industrial Estatebattery storage25approved, not built6.7
Pen Y Cae solar farmsolar farm6.9operational7.2
Coed Bach Park, Gwynfryn Roadrooftop solar15application submitted8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7587, -4.1224).