Energy Projects Near You

Solar, wind and battery projects near Llanelli (SA15)

30 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA15 (Carmarthenshire): 5 are waiting for a planning decision, 13 approved but not yet running, 5 operational. The largest live scheme is Pencoed Ganol Farm, Pendderi Road (35 MW solar farm, application submitted on 11 November 2025, no decision recorded), 5.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30projects within 10 km
5awaiting a decision
13approved, not running
5operational

Projects within 10 km of SA15

Projects of 1 MW and more (18)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Brynteg Farmsolar farmsolar farm16.2operationalupdated Mar 2015Sep 2013granted Mar 2014Mar 2015Carmarthenshire1.6
Heol Aur, Dafen Industrial Estatebattery storagebattery storage25approved, not builtupdated Apr 2026May 2025granted Feb 2026Apr 2026Carmarthenshire2.9
Glyngwernen Farm, Uchaf Fawr Solar Farmsolar farmsolar farm8.4approved, not builtupdated Mar 2025Jul 2024granted Feb 2025Mar 2025Carmarthenshire3.4
Glyngwernen Farm, Uchaf Fawrbattery storagebattery storage2approved, not builtupdated Mar 2025Jul 2024granted Feb 2025Mar 2025Carmarthenshire3.4
Morfa Ynys Farmlandssolar farmsolar farm3permission expiredupdated Oct 2019Oct 2015granted May 2016Oct 2019Carmarthenshire4.0
Llangennech Solarsolar farmsolar farm29.9approved, not built may be out of dateupdated Nov 2021Mar 2020granted Jul 2021Nov 2021Carmarthenshire4.7
Pencoed Ganol Farm, Pendderi Roadsolar farmsolar farm35application submittedupdated Mar 2026Nov 2025—Mar 2026Carmarthenshire5.0
Ffos Las Racecoursesolar farmsolar farm5.5operationalupdated Jun 2013Nov 2010granted Apr 2011Jun 2013Carmarthenshire5.6
Dura Park Bynea Industrial Siterooftop solarrooftop solar1.4operationalupdated Jun 2016Oct 2015granted Dec 2015Jun 2016Carmarthenshire6.5
Pentre farmsolar farmsolar farm5.5operationalupdated Jan 2015Dec 2012granted Mar 2013Jan 2015Carmarthenshire7.3
Y Tyddyn Teg, Heol Y Nant Solar Farmsolar farmsolar farm1approved, not builtupdated Mar 2025Jun 2024granted Jan 2025Mar 2025Carmarthenshire7.5
Rhas Fach Farmsolar farmsolar farm1.2permission expiredupdated Aug 2019Jul 2015granted Sep 2015Aug 2019Carmarthenshire7.6
Pencefnarda Uchaf Farmsolar farmsolar farm3.6refused on appealupdated Oct 2015Jun 2014refused Feb 2015Oct 2015Swansea8.3
Pont Andrew Solar Farmsolar farmsolar farm1.5operationalupdated Mar 2013Nov 2010granted Apr 2011Mar 2013Carmarthenshire8.7
Morfa Pingett Solar Farmsolar farmsolar farm1.6refusedupdated Dec 2021Aug 2021refused Oct 2021Dec 2021Carmarthenshire8.7
Coed Bach Park, Gwynfryn Roadrooftop solarrooftop solar15application submittedupdated Sep 2025Aug 2025—Sep 2025Swansea9.2
Castell Ddu Solar Farmsolar farmsolar farm5permission expiredupdated Mar 2020Sep 2015granted Jan 2016Mar 2020Swansea9.6
Pembrey Road - Ground Mounted Solar Panelssolar farmsolar farm1approved, not builtupdated Jun 2026May 2023granted Nov 2025Jun 2026Carmarthenshire9.8
Smaller schemes under 1 MW, mostly rooftop solar (12)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Andrew Street - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Apr 2026—May 2026Carmarthenshire1.8
Sandy Road Solar Panels & Biomass Boilerrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Mar 2023granted Mar 2025Mar 2025Carmarthenshire2.0
Dafen Inn Row And Exchange Rowbattery storagebattery storage0.2approved, not builtupdated Sep 2025Jul 2025granted Aug 2025Sep 2025Carmarthenshire3.0
Morrisons Supermarket, -Solar Panelsrooftop solarrooftop solar0.4approved, not builtupdated Jan 2023Oct 2022granted Dec 2022Jan 2023Carmarthenshire3.2
The Lord Arthur Rank Centre, Trostre Road - Installation of Solar Panelssolar farmsolar farm—no application requiredupdated Mar 2025——Mar 2025Carmarthenshire3.4
The Beacon Enterprise Centre, Heol Aur - Micro Battery Storagebattery storagebattery storage0.2approved, not builtupdated Jul 2026Apr 2026granted Jun 2026Jul 2026Carmarthenshire3.4
Parc Y Scarlets, Pemberton Athletics Track - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Sep 2025Aug 2025granted Sep 2025Sep 2025Carmarthenshire3.4
North Avenue, Llanelli Workshops -Micro Energy Storagebattery storagebattery storage0.2application submittedMay 2026——Carmarthenshire3.5
Lower Trostre Road - Micro Battery Storagebattery storagebattery storage0.2application submittedMay 2026——Carmarthenshire3.6
Tesco Superstore, Tidal Reachrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Dec 2025granted Jan 2026Jan 2026Swansea8.7
Ty Cwm Gwendraeth, Gwalia Mynydd Mawrrooftop solarrooftop solar—approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Carmarthenshire9.0
Heol Y Mynydd Road - Micro Energy Storagebattery storagebattery storage0.2refusedupdated Jun 2026Feb 2026refused Apr 2026Jun 2026Swansea9.6

Distance from the average position of the SA15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm15144275.3
Rooftop solar6141015.9
Battery storage9350128.2

MW in pipeline: pending, approved and under-construction capacity.

How Carmarthenshire decides solar, wind and battery applications

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in Carmarthenshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SA15, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.