Pen Y Cae solar farm (6.9 MW)

Pen Y Cae solar farm is a 6.9 MW solar farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 March 2015; the record was last updated on 2 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWsolar farm
operationalstatus in REPD
2 May 2017record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
18 April 2013Application submitted
19 September 2013Planning permission granted
3 November 2014Construction started
26 March 2015Operational

Project details

Technology
solar farm
Capacity
6.9 MW
Status (REPD)
operational
Record last updated
2 May 2017
Operator or applicant
Rockfire Capital
Planning authority
Carmarthenshire
Planning application reference
E/28086
Site area
21.0 ha
Address (REPD)
Pen Y Cae, Saron, Ammanford, Dyfed
Council area (by location)
Carmarthenshire
Time to decision
22 weeks
REPD reference
1781

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Saron Road solar parksolar farm6.7operational1.1
Clawdd Ddu PVsolar farm13.5operational1.9
Tycroes Solar Farmsolar farm40approved, not built2.1
Brynrhyd Solar Farmsolar farm36approved, not built3.9
Cefn Betingau Farmsolar farm9operational5.9
Mynydd y Betwswind farm34.5operational7.1
Pentre farmsolar farm5.5operational7.2
Mynydd Y Gwair Wind Farmwind farm32.8operational7.6
Coed Bach Park, Gwynfryn Roadrooftop solar15application submitted8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7874, -4.0291).