Energy Projects Near You

Cefn Betingau Farm (9 MW solar farm)

Cefn Betingau Farm is a 9 MW solar farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 30 April 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWsolar farm
operationalstatus in REPD
30 April 2014record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
10 June 2013Application submitted
28 August 2013Planning permission granted
31 March 2014Operational

Project details

Technology
solar farm
Capacity
9 MW
Status (REPD)
operational
Record last updated
30 April 2014
Operator or applicant
Wessex Solar Energy
Planning authority
Carmarthenshire
Planning application reference
2013/0865
Site area
21.9 ha
Address (REPD)
Land at Cefn Betingau Farm, Morriston, Swansea
Council area (by location)
Carmarthenshire
Time to decision
11 weeks
REPD reference
1330

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mynydd y Betwswind farm34.5operational2.6
Mynydd Y Gwair Wind Farmwind farm32.8operational5.0
Saron Road solar parksolar farm6.7operational5.1
Pen Y Cae solar farmsolar farm6.9operational5.9
Clawdd Ddu PVsolar farm13.5operational7.0
Tycroes Solar Farmsolar farm40approved, not built7.7
Brynrhyd Solar Farmsolar farm36approved, not built8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7942, -3.9437).