Energy Projects Near You

Solar, wind and battery projects near Ammanford (SA18)

16 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA18 (Carmarthenshire): 1 is waiting for a planning decision, 7 approved but not yet running, 7 operational. The largest live scheme is Tycroes Solar Farm (40 MW solar farm, approved on 12 August 2021, not yet built), 6.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16projects within 10 km
1awaiting a decision
7approved, not running
7operational

Projects within 10 km of SA18

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cefn Betingau Farmsolar farmsolar farm9operationalupdated Apr 2014Jun 2013granted Aug 2013Apr 2014Carmarthenshire1.2
Mynydd y Betwswind farmwind farm34.5operationalupdated Aug 2017Jun 2005granted Jun 2007Aug 2017Neath Port Talbot3.5
Saron Road solar parksolar farmsolar farm6.7operationalupdated Aug 2015Apr 2013granted Sep 2013Aug 2015Carmarthenshire4.0
Pen Y Cae solar farmsolar farmsolar farm6.9operationalupdated May 2017Apr 2013granted Sep 2013May 2017Carmarthenshire4.8
Mynydd Y Gwair Wind Farmwind farmwind farm32.8operationalupdated Apr 2019Sep 2012granted Feb 2013Apr 2019Swansea5.6
Clawdd Ddu PVsolar farmsolar farm13.5operationalupdated Aug 2014Mar 2013granted Oct 2013Aug 2014Carmarthenshire6.1
Tycroes Solar Farmsolar farmsolar farm40approved, not builtupdated Oct 2021Jun 2020granted Aug 2021Oct 2021Carmarthenshire6.7
Brynrhyd Solar Farmsolar farmsolar farm36approved, not builtupdated Aug 2025Oct 2021granted Jun 2023Aug 2025Carmarthenshire7.5
Mynydd Y Gwrhyd Windfarmwind farmwind farm4.7operationalupdated Jan 2016Dec 2010granted Mar 2013Jan 2016Neath Port Talbot8.1
Mynydd y Gwryhd Solar Farmsolar farmsolar farm2.3approved, not built may be out of dateupdated Oct 2020Jun 2020granted Nov 2020Oct 2020Neath Port Talbot8.1
New Lodge Farm Solarsolar farmsolar farm3refusedupdated Sep 2015Feb 2014refused Feb 2016Sep 2015Carmarthenshire8.2
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Park Street -Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2026Feb 2026granted Apr 2026Jun 2026Carmarthenshire2.0
Ty Parc Yr Hun, Ffordd Y Rhyd - Micro Energy Storage Projectbattery storagebattery storage0.2application submittedApr 2026——Carmarthenshire2.4
Brecon Beacon Natural Water - Ground Mounted Solar Panelssolar farmsolar farm0.6approved, not builtupdated Jan 2026Nov 2024granted Dec 2025Jan 2026Carmarthenshire5.3
Heol Parc Mawr Workshops, Cross Hands - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Oct 2025Jul 2025granted Aug 2025Oct 2025Carmarthenshire7.9
Mynydd y Gwryhd Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated Nov 2022Jun 2020granted Nov 2020Nov 2022Neath Port Talbot8.1

Distance from the average position of the SA18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm9044178.9
Wind farm300300
Battery storage413000.6

MW in pipeline: pending, approved and under-construction capacity.

How Carmarthenshire decides solar, wind and battery applications

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in Carmarthenshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SA18, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.