Mynydd Y Gwair Wind Farm (32.8 MW)

Mynydd Y Gwair Wind Farm is a 32.8 MW wind farm project in Swansea, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 April 2019; the record was last updated on 30 April 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32.8 MWwind farm
operationalstatus in REPD
30 April 2019record last updated
Swanseacouncil area

Planning timeline

DateStage
11 September 2012Application submitted
8 February 2013Planning permission granted
8 February 2017Construction started
24 April 2019Operational

Project details

Technology
wind farm
Capacity
32.8 MW
Status (REPD)
operational
Record last updated
30 April 2019
Operator or applicant
RWE Npower Renewables/ Innogy
Planning authority
Swansea
Planning application reference
2012/1221
Turbines
16
Address (REPD)
Swansea,
Council area (by location)
Swansea
Time to decision
21 weeks
Contracts for Difference
AR1
REPD reference
4648

Earlier applications for this site

ApplicationMWSubmittedOutcome
Mynydd y Gwair Wind Farm 2008/1781572 September 2008refused 12 January 2010

Who decides

ApplicationsSwanseaUK
Decided applications (solar, wind, battery)3510,236
Refused9 (26%)19%
Solar refused5 of 2012%
Onshore wind refused2 of 345%
Battery storage refused2 of 1216%
Median time from submission to decision18.1 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mynydd y Betwswind farm34.5operational2.7
Cefn Betingau Farmsolar farm9operational5.0
Abergelli Glas Solar Farmsolar farm7.7operational5.4
Abergelli Farm, Felindrebattery storage250application submitted5.9
Rhyd-y-Pandy Solar Farmsolar farm6operational5.9
Land at Lltty Morphil Farmsolar farm5abandoned6.5
Lletty Scilp Farm, Swansea Northbattery storage400approved, not built6.5
Gelliwern Isaf Farmsolar farm6operational6.6
Solar Farm at The E/O Pontlliwsolar farm40application submitted6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7492, -3.9381).