Abergelli Glas Solar Farm (7.7 MW)

Abergelli Glas Solar Farm is a 7.7 MW solar farm project in Swansea, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2015; the record was last updated on 4 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.7 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
Swanseacouncil area

Planning timeline

DateStage
18 February 2013Application submitted
28 May 2013Planning permission granted
1 November 2014Construction started
15 March 2015Operational

Project details

Technology
solar farm
Capacity
7.7 MW
Status (REPD)
operational
Record last updated
4 September 2018
Operator or applicant
Foresight
Planning authority
Swansea
Planning application reference
2013/0135
Address (REPD)
Land at Abergelli Farm Felindre Swansea
Council area (by location)
Swansea
Time to decision
14 weeks
REPD reference
1953

Who decides

ApplicationsSwanseaUK
Decided applications (solar, wind, battery)3510,236
Refused9 (26%)19%
Solar refused5 of 2012%
Onshore wind refused2 of 345%
Battery storage refused2 of 1216%
Median time from submission to decision18.1 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Abergelli Farm, Felindrebattery storage250application submitted0.5
Rhyd-y-Pandy Solar Farmsolar farm6operational0.7
Land at Lltty Morphil Farmsolar farm5abandoned1.2
Lletty Scilp Farm, Swansea Northbattery storage400approved, not built1.2
Solar Farm at The E/O Pontlliwsolar farm40application submitted1.6
Gelliwern Isaf Farmsolar farm6operational3.1
Bryntywod, Llangyfelachbattery storage200approved, not built3.1
Gwenlais Solar Farmsolar farm16.3approved, not built4.7
Craig Y Perchych, Glais Solar farmsolar farm20approved, not built5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7007, -3.9476).