Energy Projects Near You

Craig Y Perchych, Glais Solar farm (20 MW)

Craig Y Perchych, Glais Solar farm is a 20 MW solar farm project in Swansea, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 December 2024, not yet built; the record was last updated on 27 February 2026. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtstatus in REPD
27 February 2026record last updated
Swanseacouncil area

Planning timeline

DateStage
13 October 2023Application submitted
16 December 2024Planning permission granted
16 December 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
27 February 2026
Operator or applicant
Windel Energy
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3279676
Site area
68.7 ha
Address (REPD)
Craig Y Perchych Glais, Swansea
Council area (by location)
Swansea
Time to decision
61 weeks
Contracts for Difference
AR7a
Name in REPD
Craig Y Perchych, Glais - Solar farm
REPD reference
9777

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Rhyd-y-Pandy Solar Farmsolar farm6operational4.6
Abergelli Glas Solar Farmsolar farm7.7operational5.3
Abergelli Farm, Felindrebattery storage250application submitted5.6
Land at Lltty Morphil Farmsolar farm5abandoned5.8
Lletty Scilp Farm, Swansea Northbattery storage400approved, not built5.8
Solar Farm at The E/O Pontlliwsolar farm40application submitted6.3
Bryntywod, Llangyfelachbattery storage200approved, not built6.4
Carn Nicholas Farmsolar farm5under construction6.7
Carn Nicholas Farm (Extension)solar farm10operational6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6878, -3.8738).