Energy Projects Near You

Abergelli Farm, Felindre (250 MW battery storage)

Abergelli Farm, Felindre is a 250 MW battery storage project in Swansea, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 22 July 2025, no decision recorded; the record was last updated on 29 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

250 MWbattery storage
application submittedstatus in REPD
29 August 2025record last updated
Swanseacouncil area

Planning timeline

DateStage
22 July 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
250 MW
Status (REPD)
application submitted
Record last updated
29 August 2025
Operator or applicant
EDF Energy Renewables
Planning authority
Swansea
Planning application reference
2025/1580/FUL
Address (REPD)
Abergelli Farm Felindre
Council area (by location)
Swansea
Name in REPD
Abergelli Farm, Felindre - Battery Storage
REPD reference
12661

Who decides

ApplicationsSwanseaUK
Decided applications (solar, wind, battery)3510,236
Refused9 (26%)19%
Solar refused5 of 2012%
Onshore wind refused2 of 345%
Battery storage refused2 of 1216%
Median time from submission to decision18.1 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Abergelli Glas Solar Farmsolar farm7.7operational0.5
Land at Lltty Morphil Farmsolar farm5abandoned0.7
Lletty Scilp Farm, Swansea Northbattery storage400approved, not built0.7
Rhyd-y-Pandy Solar Farmsolar farm6operational0.9
Solar Farm at The E/O Pontlliwsolar farm40application submitted1.1
Bryntywod, Llangyfelachbattery storage200approved, not built2.7
Gelliwern Isaf Farmsolar farm6operational2.8
Gwenlais Solar Farmsolar farm16.3approved, not built4.3
Castell Ddu Solar Farmsolar farm5permission expired5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6973, -3.9531).