Energy Projects Near You

Carn Nicholas Farm (Extension) (10 MW solar farm)

Carn Nicholas Farm (Extension) is a 10 MW solar farm project in Swansea, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2023; the record was last updated on 5 April 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
5 April 2023record last updated
Swanseacouncil area

Planning timeline

DateStage
31 January 2020Application submitted
17 March 2021Planning permission granted
1 January 2023Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
5 April 2023
Operator or applicant
Innova Renewables Limited
Planning authority
Swansea
Planning application reference
2020/0173/FUL
Site area
19.1 ha
Address (REPD)
Land At Carn Nicholas Farm, Bonymaen, Swansea
Council area (by location)
Swansea
Time to decision
59 weeks
Contracts for Difference
AR4
REPD reference
6834

Who decides

ApplicationsSwanseaUK
Decided applications (solar, wind, battery)3510,236
Refused9 (26%)19%
Solar refused5 of 2012%
Onshore wind refused2 of 345%
Battery storage refused2 of 1216%
Median time from submission to decision18.1 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carn Nicholas Farmsolar farm5under construction<0.1
Carn Nicholas Farmsolar farm5application withdrawn<0.1
John Green Frog Power Compound, John North Road Battery Systembattery storage20approved, not built1.1
Bryntywod, Llangyfelachbattery storage200approved, not built6.0
Chosen Park, Baglan Energy Park - Unit 3 - Battery Storage Systembattery storage30approved, not built6.0
Baglan Bay Solar Farm - Phase 1solar farm5operational6.2
Baglan Bay Solar Farm - Phase 2solar farm10application withdrawn6.2
Craig Y Perchych, Glais Solar farmsolar farm20approved, not built6.7
Ton Marw Farmwind farm7.3refused7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6319, -3.9109).