Chosen Park, Baglan Energy Park - Unit 3 - Battery Storage System (30 MW)
Chosen Park, Baglan Energy Park - Unit 3 - Battery Storage System is a 30 MW battery storage project in Neath Port Talbot, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 June 2025, not yet built; the record was last updated on 8 July 2025.
30 MWbattery storage
approved, not builtstatus in REPD
8 July 2025record last updated
Neath Port Talbotcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 25 February 2025 | Application submitted |
| 19 June 2025 | Planning permission granted |
| 18 June 2030 | Permission due to expire (unless work starts) |
Project details
- Technology
- battery storage (stand-alone storage)
- Capacity
- 30 MW
- Status (REPD)
- approved, not built
- Record last updated
- 8 July 2025
- Operator or applicant
- Aldustria Energy Storage
- Planning authority
- Neath Port Talbot
- Planning application reference
- P2025/0064
- Address (REPD)
- Unit 3, Chosen Park, Lane From Brunel Way To Sewage Pumping Station, Baglan Energy Park, Neath
- Council area (by location)
- Neath Port Talbot
- Time to decision
- 16 weeks
- REPD reference
- 18342
Who decides
| Applications | Neath Port Talbot | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 38 | 10,236 |
| Refused | 10 (26%) | 19% |
| Solar refused | 0 of 12 | 12% |
| Onshore wind refused | 10 of 23 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 57.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 3 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: Neath Port Talbort, Neath Port Talbot.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Baglan Bay Solar Farm - Phase 2 | solar farm | 10 | application withdrawn | 0.9 |
| Baglan Bay Solar Farm - Phase 1 | solar farm | 5 | operational | 2.0 |
| Tylerfedwen Farm Solar Park | solar farm | 13.3 | permission expired | 2.7 |
| Ton Marw Farm | wind farm | 7.3 | refused | 3.3 |
| John Green Frog Power Compound, John North Road Battery System | battery storage | 20 | approved, not built | 5.1 |
| Pant-Y-Moch Farm | solar farm | 5 | operational | 5.1 |
| Carn Nicholas Farm (Extension) | solar farm | 10 | operational | 6.0 |
| Carn Nicholas Farm | solar farm | 5 | application withdrawn | 6.0 |
| Carn Nicholas Farm | solar farm | 5 | under construction | 6.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6271, -3.8244).