Tylerfedwen Farm Solar Park (13.3 MW)

Tylerfedwen Farm Solar Park is a 13.3 MW solar farm project in Neath Port Talbot, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 22 July 2019; the record was last updated on 14 August 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.3 MWsolar farm
permission expiredstatus in REPD
14 August 2019record last updated
Neath Port Talbotcouncil area

Planning timeline

DateStage
19 December 2013Application submitted
22 July 2014Planning permission granted
22 July 2019Permission expired

Project details

Technology
solar farm
Capacity
13.3 MW
Status (REPD)
permission expired
Record last updated
14 August 2019
Operator or applicant
Private Developer
Planning authority
Neath Port Talbot
Planning application reference
P2013/1087
Address (REPD)
Tylerfedwen Farm, Cwmafan, Port Talbot, West Glamorgan, SA12 9YA
Council area (by location)
Neath Port Talbot
Time to decision
31 weeks
REPD reference
1877

Who decides

ApplicationsNeath Port TalbotUK
Decided applications (solar, wind, battery)3810,236
Refused10 (26%)19%
Solar refused0 of 1212%
Onshore wind refused10 of 2345%
Battery storage refused0 of 316%
Median time from submission to decision57.9 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Neath Port Talbort, Neath Port Talbot.

Other large projects within 10 km

ProjectTypeMWStatuskm
Chosen Park, Baglan Energy Park - Unit 3 - Battery Storage Systembattery storage30approved, not built2.7
Baglan Bay Solar Farm - Phase 2solar farm10application withdrawn2.8
Pant-Y-Moch Farmsolar farm5operational3.3
Baglan Bay Solar Farm - Phase 1solar farm5operational3.6
Ton Marw Farmwind farm7.3refused4.3
Rhydypandy Road, Morristonbattery storage100approved, not built5.4
Mynydd Brombil Wind Farmwind farm8operational5.6
Tonmawr - Mynydd Fforch Dwm Wind Farmwind farm35approved, not built6.1
Y Bryn Wind Farmwind farm130refused6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6266, -3.7847).