Y Bryn Wind Farm (130 MW)

Y Bryn Wind Farm is a 130 MW wind farm project in Neath Port Talbot, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 21 November 2025; the record was last updated on 19 January 2026. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

130 MWwind farm
refusedstatus in REPD
19 January 2026record last updated
Neath Port Talbotcouncil area

Planning timeline

DateStage
20 December 2023Application submitted
21 November 2025Refused by the planning authority

Project details

Technology
wind farm
Capacity
130 MW
Status (REPD)
refused
Record last updated
19 January 2026
Operator or applicant
ESB / Coriolis Energy
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3264571
Turbines
18
Turbine height
250 m
Address (REPD)
Ffordd y Frenhines, Margam,
Council area (by location)
Neath Port Talbot
Time to decision
100 weeks
REPD reference
10036

The scheme also includes battery storage, recorded separately in REPD (refused).

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Mynydd Brombil Wind Farmwind farm8operational2.7
Rhydypandy Road, Morristonbattery storage100approved, not built2.9
Pant-Y-Moch Farmsolar farm5operational3.9
Foel Trawsnantwind farm35approved, not built4.0
Tylerfedwen Farm Solar Parksolar farm13.3permission expired6.5
Foel Fawrsolar farm5.1permission expired6.9
Pen Y Cymoeddwind farm228operational7.1
Pen y Cymoedd Energy Storagebattery storage22operational7.1
Tonmawr - Mynydd Fforch Dwm Wind Farmwind farm35approved, not built7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5919, -3.7097).