Pen y Cymoedd Energy Storage (22 MW)

Pen y Cymoedd Energy Storage is a 22 MW battery storage project in Neath Port Talbot, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 May 2018; the record was last updated on 3 January 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWbattery storage
operationalstatus in REPD
3 January 2019record last updated
Neath Port Talbotcouncil area

Planning timeline

DateStage
19 November 2009Application submitted
1 November 2017Construction started
1 May 2018Operational

Project details

Technology
battery storage (co-located with re)
Capacity
22 MW
Status (REPD)
operational
Record last updated
3 January 2019
Operator or applicant
Vattenfall
Planning authority
Neath Port Talbot
Planning application reference
P2009/1053
Address (REPD)
Pen y Cymoedd, Neath Port Talbot
Council area (by location)
Neath Port Talbot
REPD reference
6927

Recorded together with Pen Y Cymoedd (228 MW wind farm, operational).

Who decides

ApplicationsNeath Port TalbotUK
Decided applications (solar, wind, battery)3810,236
Refused10 (26%)19%
Solar refused0 of 1212%
Onshore wind refused10 of 2345%
Battery storage refused0 of 316%
Median time from submission to decision57.9 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Neath Port Talbort, Neath Port Talbot.

Other large projects within 10 km

ProjectTypeMWStatuskm
Tonmawr - Mynydd Fforch Dwm Wind Farmwind farm35approved, not built1.2
Foel Fawrsolar farm5.1permission expired3.2
Foel Trawsnantwind farm35approved, not built3.5
Melin Courtwind farm18approved, not built4.6
Llynfi Renewable Energy Park, Land at Mynydd Caerauwind farm24operational5.3
Ffynnon Oer Wind Farmwind farm32operational5.5
Llynfi Afan Renewable Energy Parkwind farm6operational5.8
Tylerfedwen Farm Solar Parksolar farm13.3permission expired6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6555, -3.6957).