Llynfi Renewable Energy Park, Land at Mynydd Caerau (24 MW)

Llynfi Renewable Energy Park, Land at Mynydd Caerau is a 24 MW wind farm project in Neath Port Talbot, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 September 2017; the record was last updated on 5 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWwind farm
operationalstatus in REPD
5 October 2017record last updated
Neath Port Talbotcouncil area

Planning timeline

DateStage
15 November 2010Application submitted
3 April 2012Refused by the planning authority
27 August 2013Planning permission granted
27 August 2013Appeal allowed
27 May 2016Construction started
14 September 2017Operational

Project details

Technology
wind farm
Capacity
24 MW
Status (REPD)
operational
Record last updated
5 October 2017
Operator or applicant
John Laing Environmental Assets Group
Planning authority
Neath Port Talbot
Planning application reference
P2010/1148
Turbines
12
Address (REPD)
Glyncorrwg and Gelli Mountain , Croeserw , Neath and Port Talbot
Council area (by location)
Neath Port Talbot
Time to decision
145 weeks
REPD reference
4656

Who decides

ApplicationsNeath Port TalbotUK
Decided applications (solar, wind, battery)3810,236
Refused10 (26%)19%
Solar refused0 of 1212%
Onshore wind refused10 of 2345%
Battery storage refused0 of 316%
Median time from submission to decision57.9 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Neath Port Talbort, Neath Port Talbot.

Other large projects within 10 km

ProjectTypeMWStatuskm
Llynfi Afan Renewable Energy Parkwind farm6operational0.5
Foel Fawrsolar farm5.1permission expired2.3
Werfa Wind Farmwind farm14.3refused3.1
Ogmore & Garwwind farm12refused3.5
Ffynnon Oer Wind Farmwind farm32operational4.3
Werfawind farm47.5refused on appeal4.4
Foel Trawsnantwind farm35approved, not built5.0
Pen y Cymoedd Energy Storagebattery storage22operational5.3
Pen Y Cymoeddwind farm228operational5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6449, -3.6211).