Llynfi Afan Renewable Energy Park (6 MW)

Llynfi Afan Renewable Energy Park is a 6 MW wind farm project in Neath Port Talbot, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 September 2017; the record was last updated on 20 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
operationalstatus in REPD
20 December 2017record last updated
Neath Port Talbotcouncil area

Planning timeline

DateStage
15 November 2010Application submitted
18 July 2013Planning permission granted
27 May 2016Construction started
14 September 2017Operational

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
20 December 2017
Operator or applicant
John Laing Environmental Assets Group
Planning authority
Neath Port Talbot
Planning application reference
P/10/844/FUL
Turbines
3
Address (REPD)
Mynydd Y Gelli, Port Talbot, Bridgend
Council area (by location)
Neath Port Talbot
Time to decision
139 weeks
REPD reference
4644

Who decides

ApplicationsNeath Port TalbotUK
Decided applications (solar, wind, battery)3810,236
Refused10 (26%)19%
Solar refused0 of 1212%
Onshore wind refused10 of 2345%
Battery storage refused0 of 316%
Median time from submission to decision57.9 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Neath Port Talbort, Neath Port Talbot.

Other large projects within 10 km

ProjectTypeMWStatuskm
Llynfi Renewable Energy Park, Land at Mynydd Caerauwind farm24operational0.5
Werfa Wind Farmwind farm14.3refused2.6
Foel Fawrsolar farm5.1permission expired2.7
Ogmore & Garwwind farm12refused3.1
Werfawind farm47.5refused on appeal4.0
Ffynnon Oer Wind Farmwind farm32operational4.6
Upper Ogmore Wind Farmwind farm25.2approved, not built4.9
Foel Trawsnantwind farm35approved, not built5.3
Pen Y Cymoeddwind farm228operational5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6427, -3.6147).