Energy Projects Near You

Werfa (47.5 MW wind farm)

Werfa is a 47.5 MW wind farm project in Bridgend, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 25 August 2004; the record was last updated on 31 August 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

47.5 MWwind farm
refused on appealstatus in REPD
31 August 2010record last updated
Bridgendcouncil area

Planning timeline

DateStage
28 September 2001Application submitted
13 March 2002Refused by the planning authority
25 August 2004Appeal refused

Project details

Technology
wind farm
Capacity
47.5 MW
Status (REPD)
refused on appeal
Record last updated
31 August 2010
Operator or applicant
AMEC
Planning authority
Bridgend
Planning application reference
P/01/887/FUL
Turbines
19
Address (REPD)
Nant Y Moel, Bridgend, Mid Glamorgan
Council area (by location)
Bridgend
Time to decision
24 weeks
REPD reference
2633

Who decides

ApplicationsBridgendUK
Decided applications (solar, wind, battery)1910,236
Refused7 (37%)19%
Solar refused1 of 812%
Onshore wind refused6 of 1045%
Battery storage refused0 of 116%
Median time from submission to decision23.7 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ogmore & Garwwind farm12refused0.9
Werfa Wind Farmwind farm14.3refused1.4
Upper Ogmore Wind Farmwind farm25.2approved, not built1.4
Llynfi Afan Renewable Energy Parkwind farm6operational4.0
Pant y Wal (Extension)wind farm5approved, not built4.0
Llynfi Renewable Energy Park, Land at Mynydd Caerauwind farm24operational4.4
Pant y walwind farm25operational4.7
Wind Turbines at Mynydd Y Glyn Wind Farmwind farm30approved, not built4.9
Fforch Nest Wind Farmwind farm16abandoned5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.639, -3.5577).