Fforch Nest Wind Farm (16 MW)

Fforch Nest Wind Farm is a 16 MW wind farm project in Rhondda Cynon Taf, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 6 February 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWwind farm
abandonedstatus in REPD
6 February 2013record last updated
Rhondda Cynon Tafcouncil area

Planning timeline

DateStage
23 August 2006Application submitted
25 August 2009Planning permission granted
25 August 2011Permission expired

Project details

Technology
wind farm
Capacity
16 MW
Status (REPD)
abandoned
Record last updated
6 February 2013
Operator or applicant
Npower Renewables
Planning authority
Rhondda Cynon Taf
Planning application reference
06/1688/03
Turbines
6
Address (REPD)
land north of glynogwr, Blackmill, Bridgend
Council area (by location)
Rhondda Cynon Taf
Time to decision
157 weeks
REPD reference
3834

Who decides

ApplicationsRhondda Cynon TafUK
Decided applications (solar, wind, battery)3410,236
Refused5 (15%)19%
Solar refused0 of 1312%
Onshore wind refused3 of 1545%
Battery storage refused2 of 616%
Median time from submission to decision28.9 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fforch Nest Wind Farm pt1wind farm10operational<0.1
Fforch Nest Wind Farm pt2wind farm17.5operational0.5
Pant y walwind farm25operational0.7
Mynydd Pen-y-Graig Wind Farmwind farm15application withdrawn2.1
Pant y Wal (Extension)wind farm5approved, not built2.6
Trane Renewable Energy Parkwind farm11.9application withdrawn2.8
Pant y wal extensionwind farm20operational3.3
Wind Turbines at Mynydd Y Glyn Wind Farmwind farm30approved, not built4.1
Upper Ogmore Wind Farmwind farm25.2approved, not built4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.611, -3.4947).