Energy Projects Near You

Renewable energy projects in Rhondda Cynon Taf

54 solar, wind or battery projects of 150 kW or more are located in Rhondda Cynon Taf (REPD, July 2026 extract): 12 pending, 13 approved but not running, 18 operational and 3 refused. The council refused 5 of 34 decided applications (15%; UK 19%), with a median 29 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

54projects in the council area
12awaiting a decision
13approved, not running
15%of decisions refused

How Rhondda Cynon Taf decides

ApplicationsRhondda Cynon TafUK
Decided applications (solar, wind, battery)3410,236
Refused5 (15%)19%
Solar refused0 of 1312%
Onshore wind refused3 of 1545%
Battery storage refused2 of 616%
Median time from submission to decision28.9 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Projects in Rhondda Cynon Taf

Projects of 1 MW and more (45)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Cefn Farm, Mount Roadbattery storagebattery storage200application submittedupdated Jul 2025May 2025—Jul 2025
National Road, Cilfynyddbattery storagebattery storage200application submittedupdated Aug 2025Jun 2025—Aug 2025
Pound Farm Lanebattery storagebattery storage200application submittedupdated Dec 2025Nov 2025—Dec 2025
Solar Array at Bryntail Roadsolar farmsolar farm39.9application submittedupdated Oct 2025May 2025—Oct 2025
Llanwonno Wind Farmsolar farmsolar farm30.7application submittedupdated Apr 2025Mar 2025—Apr 2025
Llanwonno Wind Farmwind farmwind farm30.4application submittedupdated Apr 2025Mar 2025—Apr 2025
Wind Turbines at Mynydd Y Glyn Wind Farmwind farmwind farm30approved, not builtupdated Jan 2026May 2023granted Jun 2024Jan 2026
Maes Mawr Solarsolar farmsolar farm30under constructionupdated Jul 2026Dec 2022granted Dec 2023Jul 2026
Llanwonno Wind Farmbattery storagebattery storage30application submittedupdated Apr 2025Mar 2025—Apr 2025
Pant y walwind farmwind farm25operationalupdated Jun 2013Mar 2006granted May 2011Jun 2013
Hirwaun Wind Farmwind farmwind farm24refused on appealupdated Jul 2010Jul 2006refused Oct 2007Jul 2010
Maerdywind farmwind farm24operationalupdated Jun 2014Sep 2006granted Feb 2008Jun 2014
Mynydd Bwllfa Wind Farm - Resubmissionwind farmwind farm22.5operationalupdated Aug 2015May 2009granted Jun 2012Aug 2015
Hirwaun Stor Generationbattery storagebattery storage21.8operationalupdated Mar 2025Jan 2021granted Apr 2021Mar 2025
Energy Centre Royal Mintbattery storagebattery storage20operationalupdated Aug 2023Sep 2019granted Jan 2020Aug 2023
Blaencorrwg Wind Farmwind farmwind farm19.3refusedupdated Sep 2003Jul 1994refused Nov 1994Sep 2003
Fforch Nest Wind Farm pt2wind farmwind farm17.5operationalupdated Jun 2013Mar 2006granted May 2011Jun 2013
Headwind Taff Ely Wind Farm (Repowering)wind farmwind farm17.5permission expiredupdated Feb 2020Dec 2011granted Apr 2013Feb 2020
Fforch Nest Wind Farmwind farmwind farm16abandonedupdated Feb 2013Aug 2006granted Aug 2009Feb 2013
Mynydd Pen-y-Graig Wind Farmwind farmwind farm15application withdrawnupdated Sep 2016Jun 2015—Sep 2016
Abergorki Wind Farmwind farmwind farm13.5approved, not built may be out of dateupdated Nov 2024Jun 2013granted Jul 2015Nov 2024
Mynydd Portref Wind Farm extensionwind farmwind farm12operationalupdated Apr 2017Jun 2012granted Dec 2014Apr 2017
Trane Renewable Energy Parkwind farmwind farm11.9application withdrawnupdated Jun 2010——Jun 2010
Fforch Nest Wind Farm pt1wind farmwind farm10operationalupdated Jun 2013Aug 2006granted May 2011Jun 2013
Talbot Green, Llantrisant Solar Farmsolar farmsolar farm9.9approved, not builtupdated Feb 2026Dec 2022granted Apr 2024Feb 2026
Dyffryn Farm, Ynysmaerdysolar farmsolar farm9.9application submittedupdated Jan 2026Dec 2025—Jan 2026
Rhigos Road Solar Farmsolar farmsolar farm9.9under constructionupdated Feb 2026Nov 2023granted Jun 2024Feb 2026
Mynydd Portrefwind farmwind farm9.4operationalupdated Jun 2018Jun 2006granted Jul 2008Jun 2018
Taff Ely Wind Farmwind farmwind farm9operationalupdated Jun 2011——Jun 2011
Bryngolwg Farm, Hirwaun Solar farmsolar farmsolar farm8.9operationalupdated Jan 2024Jun 2022granted Jun 2022Jan 2024
Mynydd Bwllfa solar farmsolar farmsolar farm7.5permission expiredupdated Jun 2020Apr 2014granted Apr 2019Jun 2020
Llwyncelyn Wind Farmwind farmwind farm7.2application submitted may be out of dateupdated Oct 2018Aug 2018—Oct 2018
Penrhys Wind Farm/Ferndale Power Factorywind farmwind farm6.4operationalupdated Nov 2013Feb 2003granted Mar 2005Nov 2013
Coed Ely Solar Farmsolar farmsolar farm6under constructionupdated Apr 2025Sep 2023granted Dec 2023Apr 2025
Berthlwyd Farmsolar farmsolar farm5operationalupdated Dec 2017Jun 2015granted Mar 2016Dec 2017
Maes Bach Farmsolar farmsolar farm4.9operationalupdated Dec 2015Jul 2014granted Dec 2014Dec 2015
Rhondda Valley Solar Farmsolar farmsolar farm4.8application withdrawnupdated Dec 2014Mar 2011—Dec 2014
Pen Rhiw Caradogsolar farmsolar farm4.7operationalupdated May 2017Sep 2013granted Jul 2016May 2017
Agricultural Land at Trecastlesolar farmsolar farm4operationalupdated Jan 2016Mar 2015granted Oct 2015Jan 2016
Maerdy extensionwind turbinewind turbine3abandonedupdated May 2015May 2014granted Dec 2014May 2015
Graig Fatha Farmwind turbinewind turbine2.5operationalupdated Mar 2023May 2017granted Jun 2017Mar 2023
Malthouse Farmwind turbinewind turbine1.5application withdrawnupdated Dec 2015Jul 2014—Dec 2015
West of Rhiwfelin Fach Farmwind turbinewind turbine1.5operationalupdated Sep 2018Feb 2016granted Jul 2016Sep 2018
Former Nant-y-Gwyddon Landfill Sitewind turbinewind turbine1.5under constructionupdated Aug 2023Mar 2017granted Aug 2017Aug 2023
Whitehall Farm, Llanharry Roadsolar farmsolar farm1.3under constructionupdated Jul 2025Jul 2024granted Sep 2024Jul 2025
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Midway Retail Parkrooftop solarrooftop solar0.9approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024
Rhiwfelin Fach Farm, Ynysmaerdysolar farmsolar farm0.5approved, not builtupdated Apr 2022Dec 2021granted Mar 2022Apr 2022
Ynyswen Industrial Estate, Ynys-Wen - Unit 36 - Battery Energy Storagebattery storagebattery storage0.4approved, not builtupdated Mar 2025Mar 2025granted May 2025Mar 2025
Amgen Cymru Limited, Bryn Pica Waste Disposal,Merthyr Roadsolar farmsolar farm0.3approved, not builtupdated Apr 2023Jan 2023granted Apr 2023Apr 2023
Amgen Cymru Limited, Bryn Pica Wastesolar farmsolar farm0.3application submittedupdated May 2025Apr 2025—May 2025
Abercwmboi Rugby Club, Aberaman - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated May 2025Dec 2024granted Apr 2025May 2025
Harriet Street - Micro Energy Storagebattery storagebattery storage0.2refusedupdated Feb 2026Nov 2025refused Jan 2026Feb 2026
Coedcae Industrial Estate, Talbot Green - Micro Energy Storage Systemsbattery storagebattery storage0.2application submittedupdated Feb 2026Jan 2026—Feb 2026
Llanwonno Road, Ferndale Road - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated Feb 2026Jan 2026—Feb 2026

Postcode districts in Rhondda Cynon Taf

DistrictProjects within 10 kmPendingApprovedOperational
CF373310710
CF38329810
CF3944111314
CF404481214
CF41362912
CF424031014
CF4336799
CF4426387
CF4528865
CF723571112

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Rhondda Cynon Taf by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.