Energy Projects Near You

Mynydd Bwllfa solar farm (7.5 MW)

Mynydd Bwllfa solar farm is a 7.5 MW solar farm project in Rhondda Cynon Taf, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired; the record was last updated on 5 June 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWsolar farm
permission expiredstatus in REPD
5 June 2020record last updated
Rhondda Cynon Tafcouncil area

Planning timeline

DateStage
11 April 2014Application submitted
30 April 2019Planning permission granted

Project details

Technology
solar farm
Capacity
7.5 MW
Status (REPD)
permission expired
Record last updated
5 June 2020
Operator or applicant
Walters Group
Planning authority
Rhondda Cynon Taf
Planning application reference
14/0466/10
Address (REPD)
E/O Mynydd Bwllfa Wind Farm, Aberdare,
Council area (by location)
Rhondda Cynon Taf
Time to decision
264 weeks
REPD reference
1936

Who decides

ApplicationsRhondda Cynon TafUK
Decided applications (solar, wind, battery)3410,236
Refused5 (15%)19%
Solar refused0 of 1312%
Onshore wind refused3 of 1545%
Battery storage refused2 of 616%
Median time from submission to decision28.9 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hirwaun Wind Farmwind farm24refused on appeal1.1
Mynydd Bwllfa Wind Farm - Resubmissionwind farm22.5operational1.1
Maerdywind farm24operational2.8
Hirwaun Stor Generationbattery storage21.8operational4.0
Rhigos Road Solar Farmsolar farm9.9under construction4.1
Abergorki Wind Farmwind farm13.5approved, not built4.4
Cefn Farm, Mount Roadbattery storage200application submitted4.5
Bryngolwg Farm, Hirwaun Solar farmsolar farm8.9operational4.8
Hendre Fawr Farmsolar farm11.6operational6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7197, -3.4967).