Hirwaun Wind Farm (24 MW)

Hirwaun Wind Farm is a 24 MW wind farm project in Rhondda Cynon Taf, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 27 November 2008; the record was last updated on 6 July 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWwind farm
refused on appealstatus in REPD
6 July 2010record last updated
Rhondda Cynon Tafcouncil area

Planning timeline

DateStage
14 July 2006Application submitted
12 October 2007Refused by the planning authority
27 November 2008Appeal refused

Project details

Technology
wind farm
Capacity
24 MW
Status (REPD)
refused on appeal
Record last updated
6 July 2010
Operator or applicant
Pennant Walters
Planning authority
Rhondda Cynon Taf
Planning application reference
06/1415
Turbines
12
Address (REPD)
South of Hirwaun
Council area (by location)
Rhondda Cynon Taf
Time to decision
65 weeks
REPD reference
3549

Who decides

ApplicationsRhondda Cynon TafUK
Decided applications (solar, wind, battery)3410,236
Refused5 (15%)19%
Solar refused0 of 1312%
Onshore wind refused3 of 1545%
Battery storage refused2 of 616%
Median time from submission to decision28.9 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mynydd Bwllfa Wind Farm - Resubmissionwind farm22.5operational<0.1
Mynydd Bwllfa solar farmsolar farm7.5permission expired1.1
Maerdywind farm24operational2.0
Rhigos Road Solar Farmsolar farm9.9under construction3.8
Abergorki Wind Farmwind farm13.5approved, not built3.8
Hirwaun Stor Generationbattery storage21.8operational3.8
Cefn Farm, Mount Roadbattery storage200application submitted4.2
Bryngolwg Farm, Hirwaun Solar farmsolar farm8.9operational4.5
Blaencorrwg Wind Farmwind farm19.3refused5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7147, -3.5098).