Energy Projects Near You

Abergorki Wind Farm (13.5 MW)

Abergorki Wind Farm is a 13.5 MW wind farm project in Rhondda Cynon Taf, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 July 2015, not yet built; the record was last updated on 4 November 2024. REPD records the planning permission as expiring on 23 July 2018, but the project holds a Contracts for Difference award (AR6), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.5 MWwind farm
approved, not builtmay be out of datestatus in REPD
4 November 2024record last updated
Rhondda Cynon Tafcouncil area

REPD records the planning permission as expiring on 23 July 2018, but the project holds a Contracts for Difference award (AR6), so construction may have started.

Planning timeline

DateStage
27 June 2013Application submitted
23 July 2015Planning permission granted
23 July 2018Permission expired

Project details

Technology
wind farm
Capacity
13.5 MW
Status (REPD)
approved, not built
Record last updated
4 November 2024
Operator or applicant
Thrive Renewables
Planning authority
Rhondda Cynon Taf
Planning application reference
13/0663/10
Turbines
3
Turbine height
150 m
Address (REPD)
Craig yr Aber, Land North-East of Ffoch-orky, Treorchy, Rhondda Cynon Taf
Council area (by location)
Rhondda Cynon Taf
Time to decision
108 weeks
Contracts for Difference
AR6
REPD reference
4198

Who decides

ApplicationsRhondda Cynon TafUK
Decided applications (solar, wind, battery)3410,236
Refused5 (15%)19%
Solar refused0 of 1312%
Onshore wind refused3 of 1545%
Battery storage refused2 of 616%
Median time from submission to decision28.9 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Maerdywind farm24operational2.1
Hirwaun Wind Farmwind farm24refused on appeal3.8
Mynydd Bwllfa Wind Farm - Resubmissionwind farm22.5operational3.8
Wind Turbines at Mynydd Y Glyn Wind Farmwind farm30approved, not built3.8
Mynydd Bwllfa solar farmsolar farm7.5permission expired4.4
Penrhys Wind Farm/Ferndale Power Factorywind farm6.4operational4.9
Werfawind farm47.5refused on appeal5.9
Werfa Wind Farmwind farm14.3refused6.5
Ogmore & Garwwind farm12refused6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6806, -3.5041).