Solar, wind and battery projects near Mountain Ash (CF45)
28 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CF45 (Rhondda Cynon Taf): 8 are waiting for a planning decision, 6 approved but not yet running, 5 operational. The largest live scheme is National Road, Cilfynydd (200 MW battery storage, application submitted on 16 June 2025, no decision recorded), 5.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CF45
Projects of 1 MW and more (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Pen Rhiw Caradogsolar farm | solar farm | 4.7 | operationalupdated May 2017 | Sep 2013 | granted Jul 2016 | May 2017 | Rhondda Cynon Taf | 1.3 |
| Tir Nyth Soalr Parksolar farm | solar farm | 5 | refusedupdated May 2016 | Jul 2015 | refused Mar 2016 | May 2016 | Merthyr Tydfil | 4.3 |
| Llwyncelyn Wind Farmwind farm | wind farm | 7.2 | application submitted may be out of dateupdated Oct 2018 | Aug 2018 | — | Oct 2018 | Rhondda Cynon Taf | 5.3 |
| National Road, Cilfynyddbattery storage | battery storage | 200 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 | Rhondda Cynon Taf | 5.6 |
| Hendai Farmsolar farm | solar farm | 13.4 | operationalupdated Mar 2015 | Dec 2013 | granted Apr 2014 | Mar 2015 | Caerphilly | 5.9 |
| Bedlinog Wind Farmwind farm | wind farm | 6 | application withdrawnupdated Sep 2013 | Sep 2011 | — | Sep 2013 | Merthyr Tydfil | 6.4 |
| Penrhys Wind Farm/Ferndale Power Factorywind farm | wind farm | 6.4 | operationalupdated Nov 2013 | Feb 2003 | granted Mar 2005 | Nov 2013 | Rhondda Cynon Taf | 6.5 |
| Gelligaer 'A' Wind Farmwind farm | wind farm | 9.8 | application withdrawnupdated Jun 2002 | Aug 1999 | — | Jun 2002 | Caerphilly | 7.2 |
| Gelligaer 'B' Wind Farmwind farm | wind farm | 9.8 | application withdrawnupdated Jun 2002 | — | — | Jun 2002 | Caerphilly | 7.2 |
| Rhondda Valley Solar Farmsolar farm | solar farm | 4.8 | application withdrawnupdated Dec 2014 | Mar 2011 | — | Dec 2014 | Rhondda Cynon Taf | 7.3 |
| Llanwonno Wind Farmsolar farm | solar farm | 30.7 | application submittedupdated Apr 2025 | Mar 2025 | — | Apr 2025 | Rhondda Cynon Taf | 7.6 |
| Llanwonno Wind Farmwind farm | wind farm | 30.4 | application submittedupdated Apr 2025 | Mar 2025 | — | Apr 2025 | Rhondda Cynon Taf | 7.6 |
| Llanwonno Wind Farmbattery storage | battery storage | 30 | application submittedupdated Apr 2025 | Mar 2025 | — | Apr 2025 | Rhondda Cynon Taf | 7.6 |
| Fochriw Windwind farm | wind farm | 1.7 | application withdrawnupdated Nov 2012 | Dec 2005 | — | Nov 2012 | Caerphilly | 7.9 |
| Solar Array at Bryntail Roadsolar farm | solar farm | 39.9 | application submittedupdated Oct 2025 | May 2025 | — | Oct 2025 | Rhondda Cynon Taf | 8.5 |
| Former Nant-y-Gwyddon Landfill Sitewind turbine | wind turbine | 1.5 | under constructionupdated Aug 2023 | Mar 2017 | granted Aug 2017 | Aug 2023 | Rhondda Cynon Taf | 8.9 |
| Wind Turbines at Mynydd Y Glyn Wind Farmwind farm | wind farm | 30 | approved, not builtupdated Jan 2026 | May 2023 | granted Jun 2024 | Jan 2026 | Rhondda Cynon Taf | 9.0 |
| Cwmbargoed Disposal Pointwind turbine | wind turbine | 1.5 | refused on appealupdated Jan 2018 | Jan 2017 | refused Mar 2017 | Jan 2018 | Caerphilly | 9.0 |
| Land At Cwm Bargoedsolar farm | solar farm | 5 | operationalupdated Mar 2017 | Jun 2015 | granted Sep 2015 | Mar 2017 | Caerphilly | 9.1 |
| Twyn Hywel Wind Farmwind farm | wind farm | 92.4 | approved, not builtupdated Feb 2026 | Jun 2023 | granted Nov 2024 | Feb 2026 | Caerphilly | 9.7 |
| Berthlwyd Farmsolar farm | solar farm | 5 | operationalupdated Dec 2017 | Jun 2015 | granted Mar 2016 | Dec 2017 | Rhondda Cynon Taf | 9.8 |
| Abergorki Wind Farmwind farm | wind farm | 13.5 | approved, not built may be out of dateupdated Nov 2024 | Jun 2013 | granted Jul 2015 | Nov 2024 | Rhondda Cynon Taf | 9.9 |
| Mynydd Pen-y-Graig Wind Farmwind farm | wind farm | 15 | application withdrawnupdated Sep 2016 | Jun 2015 | — | Sep 2016 | Rhondda Cynon Taf | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Abercwmboi Rugby Club, Aberaman - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Dec 2024 | granted Apr 2025 | May 2025 | Rhondda Cynon Taf | 5.1 |
| Llanwonno Road, Ferndale Road - Micro Energy Storagebattery storage | battery storage | 0.2 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | Rhondda Cynon Taf | 5.8 |
| Harriet Street - Micro Energy Storagebattery storage | battery storage | 0.2 | refusedupdated Feb 2026 | Nov 2025 | refused Jan 2026 | Feb 2026 | Rhondda Cynon Taf | 9.1 |
| Amgen Cymru Limited, Bryn Pica Waste Disposal,Merthyr Roadsolar farm | solar farm | 0.3 | approved, not builtupdated Apr 2023 | Jan 2023 | granted Apr 2023 | Apr 2023 | Rhondda Cynon Taf | 9.1 |
| Amgen Cymru Limited, Bryn Pica Wastesolar farm | solar farm | 0.3 | application submittedupdated May 2025 | Apr 2025 | — | May 2025 | Rhondda Cynon Taf | 9.2 |
Distance from the average position of the CF45 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 3 | 1 | 4 | 1 | 71.2 |
| Wind farm | 11 | 2 | 3 | 1 | 0 | 174 |
| Wind turbine | 2 | 0 | 1 | 0 | 1 | 1.5 |
| Battery storage | 5 | 3 | 1 | 0 | 1 | 230 |
MW in pipeline: pending, approved and under-construction capacity.
How Rhondda Cynon Taf decides solar, wind and battery applications
| Applications | Rhondda Cynon Taf | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 34 | 10,236 |
| Refused | 5 (15%) | 19% |
| Solar refused | 0 of 13 | 12% |
| Onshore wind refused | 3 of 15 | 45% |
| Battery storage refused | 2 of 6 | 16% |
| Median time from submission to decision | 28.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 2 | — |
All projects in Rhondda Cynon Taf
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CF45, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.