Land At Cwm Bargoed (5 MW solar farm)

Land At Cwm Bargoed is a 5 MW solar farm project in Caerphilly, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 January 2016; the record was last updated on 24 March 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
24 March 2017record last updated
Caerphillycouncil area

Planning timeline

DateStage
1 June 2015Application submitted
17 September 2015Planning permission granted
25 November 2015Construction started
20 January 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
24 March 2017
Operator or applicant
Kronos Solar/ Vogt Solar
Planning authority
Caerphilly
Planning application reference
P/15/0169
Site area
15.1 ha
Address (REPD)
Land At Cwm Bargoed, West of, Fochriw Road, Cwmbargoed, Merthyr Tydfil, Mid Glamorgan
Council area (by location)
Caerphilly
Time to decision
15 weeks
REPD reference
5292

Who decides

ApplicationsCaerphillyUK
Decided applications (solar, wind, battery)1410,236
Refused4 (29%)19%
Solar refused0 of 712%
Onshore wind refused4 of 645%
Battery storage refused0 of 116%
Median time from submission to decision14.9 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Convatec Green Manufacturing Hubwind farm15refused2.4
Convatec Green Manufacturing Hubsolar farm5refused2.4
Gelligaer 'A' Wind Farmwind farm9.8application withdrawn2.7
Gelligaer 'B' Wind Farmwind farm9.8application withdrawn2.7
Pen March Wind Farmwind farm30refused3.8
Bedlinog Wind Farmwind farm6application withdrawn3.9
Merthyr Commonwind farm24.3refused4.7
Wauntysswg Farm, near Tredagarsolar farm30approved, not built4.9
Tir Nyth Soalr Parksolar farm5refused5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7461, -3.3172).