Energy Projects Near You

Convatec Green Manufacturing Hub (15 MW wind farm)

Convatec Green Manufacturing Hub is a 15 MW wind farm project in Caerphilly, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 19 November 2025; the record was last updated on 19 January 2026. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
refusedstatus in REPD
19 January 2026record last updated
Caerphillycouncil area

Planning timeline

DateStage
3 April 2025Application submitted
19 November 2025Refused by the planning authority

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
refused
Record last updated
19 January 2026
Operator or applicant
Convatec Limited
Planning authority
Welsh Government (NSIP)
Planning application reference
CAS-02977-Y9F1W7
Turbines
3
Turbine height
150 m
Address (REPD)
Unit 1 - 2 Heads Of The Valleys Industrial Estate, Rhymney, Tredegar
Council area (by location)
Caerphilly
Time to decision
33 weeks
REPD reference
15554

The scheme also includes 5 MW of solar farm, recorded separately in REPD (refused).

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Land At Cwm Bargoedsolar farm5operational2.4
Pen March Wind Farmwind farm30refused3.1
Wauntysswg Farm, near Tredagarsolar farm30approved, not built3.7
Merthyr Commonwind farm24.3refused4.1
Gelligaer 'A' Wind Farmwind farm9.8application withdrawn4.5
Gelligaer 'B' Wind Farmwind farm9.8application withdrawn4.5
Bedlinog Wind Farmwind farm6application withdrawn5.5
Rassau Industrial Estate, Rassaubattery storage8approved, not built6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7627, -3.2954).